Skip to content

Free practice test

Oregon CCB Test Practice Test

Practice for the test Oregon's Construction Contractors Board gives after the pre-license training, on what is Oregon's own: who must be licensed and the endorsements, bonds and insurance, the notices a residential contract needs, construction liens, CCB disputes and Oregon employer rules. Pick an answer to see whether it is right and the statute or rule behind it.

39
practice questions
each with its answer explained
5
sections
Licensing and endorsements, Bonds, insurance and the RMI, Contracts and required notices, Construction liens, CCB complaints, discipline and lead paint
70%
to pass the real exam
as its official rules state

What the real exam is like

Passing it after the pre-license training is what the Oregon Construction Contractors Board asks of a new contractor's responsible managing individual before it issues a license.

  • Each new contractor's responsible managing individual (RMI) takes the training and passes the Oregon exam; the RMI must be an owner or employee who manages or supervises construction. (CCB: How to Get a License, Required pre-license training)
  • The exam is based on the Oregon version of the NASCLA Contractors Guide to Business, Law and Project Management (2nd edition), and it is an open-book exam using that manual. (CCB: How to Get a License, About the Oregon exam)
  • The exam has 80 multiple choice questions, you have three hours, and a passing score is 70 percent (56 correct answers). The exam fee is $60, paid directly to PSI. (CCB: How to Get a License, About the Oregon exam)
  • Applicants first complete 16 hours of pre-license training from an approved provider, which alerts the testing vendor PSI so the candidate can register and schedule the exam. Scores are given immediately after the test. (CCB: How to Get a License, Required pre-license training)
  • The manual may be highlighted, underlined, tabbed and annotated before the session, but no loose paper is allowed in the testing facility and nothing may be written in the manual during the exam. (CCB: How to Get a License, About the Oregon exam)

The practice test

Pick an answer to see whether it is right. Each explanation shows why, with the rule or the working behind it, so a wrong answer still teaches you something.

0 of 39 answered

Licensing and endorsements (8) · Bonds, insurance and the RMI (8) · Contracts and required notices (8) · Construction liens (8) · CCB complaints, discipline and lead paint (7)

Licensing and endorsements

Who must hold a CCB license, the endorsement classes, exemptions, license terms and what an unlicensed contractor loses.

  1. 1. How long is an Oregon CCB contractor license valid from the date of issuance?

    Show the answer

    A. Two years. A license is valid for two years from issuance unless it is revoked or suspended. After that it must be renewed, and a lapsed license can be renewed only within two years of lapsing.

    From ORS 701.063(1)

  2. 2. Under Oregon law, which business is classed as a nonexempt independent contractor and must carry workers' compensation coverage?

    Show the answer

    B. A corporation with one or more employees. Sole proprietorships, partnerships, corporations and LLCs with one or more employees (or a PEO relationship) are nonexempt. Businesses with no employees whose owners are all in one family are generally exempt.

    From ORS 701.035(2)

  3. 3. A person works on one project under contracts totaling less than $1,000, and the work is casual, minor or inconsequential. When does this person lose the exemption from licensing?

    Show the answer

    C. When the person advertises or displays a sign or card suggesting he is a contractor. Work under $1,000 that is casual, minor and inconsequential is exempt, but the exemption does not apply to a person who advertises or uses any sign, card or device that might indicate to the public that he is a contractor.

    From ORS 701.010(4)

  4. 4. A contractor was not licensed and properly endorsed when he bid the job and while he performed it. Absent a statutory exception, what is he barred from doing for payment on that work?

    Show the answer

    D. Perfecting a construction lien, filing a CCB complaint, or suing or arbitrating for compensation. ORS 701.131 bars an unlicensed or improperly endorsed contractor from perfecting a lien, filing a CCB complaint, or starting arbitration or court claims for compensation on work subject to the chapter.

    From ORS 701.131(1)

  5. 5. What limits apply to a residential limited contractor?

    Show the answer

    A. No more than $40,000 in gross annual volume and no contract over $5,000. A residential limited contractor may not do more than $40,000 in gross annual volume or enter any contract above $5,000.

    From ORS 701.038

  6. 6. A licensed contractor moves his license to inactive status. Which statement is correct?

    Show the answer

    B. He is not subject to the bond and insurance requirements, but the license cannot be used to bid or pull permits. An inactive license is not subject to the bond or insurance requirements, but it is not a valid license for bidding, obtaining a building permit or performing work. A license may be inactive only once in a two-year term.

    From ORS 701.063(5)

  7. 7. A contractor passes the CCB exam. Within how many months must he apply for the CCB license?

    Show the answer

    C. 24 months. The CCB's licensing page states a person must apply for the license within 24 months of passing the test. A contractor whose license has lapsed more than 24 months must retake the training and exam.

    From CCB: How to Get a License, Key Deadlines

  8. 8. May a licensed Oregon contractor hire an unlicensed subcontractor for work that requires a license?

    Show the answer

    D. No, unless the subcontractor is exempt from licensure under ORS 701.010. A contractor may not hire a contractor to perform work unless that contractor is licensed and properly endorsed for the work or is exempt under ORS 701.010.

    From ORS 701.026(1)

Bonds, insurance and the RMI

Surety bond and liability insurance amounts by endorsement, the responsible managing individual, and workers' compensation.

  1. 9. What are the minimum surety bond and general liability insurance amounts for a residential general contractor?

    Show the answer

    A. $25,000 bond and $500,000 insurance. A residential general contractor must carry a $25,000 surety bond and at least $500,000 of general liability insurance (the bond rose by $5,000 from $20,000 on 1 January 2024).

    From ORS 701.081(1)

  2. 10. What are the minimum bond and general liability insurance amounts for a residential specialty contractor?

    Show the answer

    B. $20,000 bond and $300,000 insurance. A residential specialty contractor needs a $20,000 bond and at least $300,000 of general liability insurance. The $100,000 insurance figure belongs to the residential limited endorsement.

    From ORS 701.081(2)

  3. 11. What is the surety bond amount for a commercial general contractor level 1?

    Show the answer

    C. $80,000. A commercial general contractor level 1 must file an $80,000 bond (and carry at least $2 million of insurance). $75,000 was the amount before 1 January 2024.

    From ORS 701.084(1)

  4. 12. What is the minimum liability insurance for a commercial specialty contractor level 2, and what is its bond?

    Show the answer

    D. $500,000 insurance and a $25,000 bond. A commercial specialty contractor level 2 needs at least $500,000 of general liability insurance and a $25,000 bond. Commercial general level 2 needs $1 million of insurance.

    From ORS 701.084(4)

  5. 13. A contractor will hold both a residential and a commercial endorsement. How many surety bonds must be filed?

    Show the answer

    A. One bond for each endorsement, each in its required amount. An applicant for both endorsements must file a surety bond for each endorsement in the amount set for it. The CCB notes only one certificate of insurance is needed for a dual endorsement.

    From ORS 701.068(2)

  6. 14. The responsible managing individual (RMI) leaves the business. For how long may the business operate with a temporary RMI?

    Show the answer

    B. The earlier of 14 days after notifying the CCB or the date the CCB approves a new RMI. A business may operate with a temporary RMI for the earlier of 14 days after giving the CCB notice or the date it is told the board has approved the designated individual.

    From ORS 701.093(2)

  7. 15. Which statement about the RMI is correct?

    Show the answer

    C. The RMI must be an owner or employee who manages or supervises construction, and may be the RMI on only one license at a time. The RMI must have management or supervisory authority over construction activities, and may be listed as an RMI employee on only one license at a time.

    From CCB: Responsible Managing Individual

  8. 16. Which contractors must carry workers' compensation insurance under the CCB's rules?

    Show the answer

    D. Nonexempt contractors, meaning businesses that hire or lease employees, and commercial contractors. Workers' compensation is required if the business has employees, and commercial contractors must have it. Exempt contractors without employees do not need it. Exempt commercial licensees must still maintain coverage under ORS 656.128.

    From CCB: Workers Compensation Insurance

Contracts and required notices

The written residential contract rule, the three consumer notices, cancellation rights, warranties and payment rules.

  1. 17. Above what aggregate price must a contractor have a written contract for work on a residential structure?

    Show the answer

    A. $2,000. A contractor may not perform residential work for a property owner without a written contract if the aggregate contract price exceeds $2,000. Lack of a written contract does not void the contract.

    From ORS 701.305(1)

  2. 18. A residential job starts under $2,000, but the price will now exceed $2,000. How soon must the contractor deliver a written contract?

    Show the answer

    B. Not later than five days after he knows or should know the price will exceed $2,000. When the price grows past $2,000, the contractor must mail or deliver a written contract no later than five days after he knows or reasonably should know of it.

    From ORS 701.305(1)

  3. 19. Which three notices must a contractor give an owner on a residential contract above $2,000?

    Show the answer

    C. Information Notice to Owner About Construction Liens, Consumer Protection Notice, and Notice of Procedure. The CCB requires the Information Notice to Owner About Construction Liens (ORS 87.093), the Consumer Protection Notice and the Notice of Procedure (ORS 701.330), with proof of receipt retained.

    From CCB: Contractor Tools, Required Notices for Residential Construction

  4. 20. For how long must a contractor keep proof that the required residential notices were delivered?

    Show the answer

    D. Two years after the contract is entered into. The CCB says a contractor must keep proof of delivery of the required notices for two years after the contract is entered into.

    From CCB: Contractor Tools, Required Notices for Residential Construction

  5. 21. Under ORS 701.310, until when may a property owner cancel an initial written residential contract?

    Show the answer

    A. 12 midnight at the end of the next business day. The owner may cancel by written notice any time before 12 midnight at the end of the next business day. The right ends if both parties agree work begins sooner, or once the contractor substantially begins the work.

    From ORS 701.310

  6. 22. A contractor agrees to build a new house. What must he offer in writing?

    Show the answer

    B. A warranty against defects in materials and workmanship. A contractor building or selling a new residential structure must make a written offer of a warranty against defects in materials and workmanship. The owner may accept or refuse it. Manufactured dwellings are excluded.

    From ORS 701.320(1)

  7. 23. Which clause may a contract for work on a residential structure NOT contain?

    Show the answer

    C. A clause limiting the owner's right to file a CCB complaint. A residential contract may not limit the right to file a complaint with the CCB. It may require mediation or arbitration.

    From ORS 701.315

  8. 24. A contractor accepts a home improvement deposit above what percentage of the total contract price, then fails to perform or to return it within 10 days of a reasonable demand, and so may be placed on probation?

    Show the answer

    D. 50 percent. The CCB may place a contractor on probation if he accepts a deposit of more than 50 percent of a home improvement contract and fails to perform or fails to return the deposit within 10 days after a reasonable demand.

    From ORS 701.312

Construction liens

ORS chapter 87: who has lien rights, notice of right to lien, perfecting and foreclosing a lien, and the Information Notice to Owner.

  1. 25. Within how many days must a contractor who supplied labor or materials perfect a construction lien, counted from when he stopped providing labor or materials (or from completion of construction, whichever is earlier)?

    Show the answer

    A. 75 days. A lien under ORS 87.010(1) or (2) must be perfected by filing a claim of lien within 75 days after the claimant ceased providing labor or materials, or 75 days after completion of construction, whichever is earlier.

    From ORS 87.035(1)

  2. 26. After a claim of lien is filed, within how many days must suit to enforce it be brought, absent an extended payment agreement?

    Show the answer

    B. 120 days. A lien binds the improvement for no more than 120 days after the claim is filed unless suit is brought to enforce it within that time.

    From ORS 87.055

  3. 27. A supplier who wants to foreclose a lien must deliver written notice of intent to foreclose to the owner and mortgagee how long before suit starts?

    Show the answer

    C. Not later than 10 days before commencing the suit. A person intending to foreclose must deliver written notice of intent to the owner and mortgagee not later than 10 days before commencing suit. Failing to do so costs the plaintiff costs and attorney fees.

    From ORS 87.057(1)

  4. 28. Who must give an owner a Notice of Right to a Lien on a residential job where the materials or labor were not furnished at the owner's request?

    Show the answer

    D. Subcontractors, material suppliers and equipment renters. A person furnishing materials, equipment or labor not at the owner's request must give the owner a notice of right to a lien. The CCB describes it as delivered by subcontractors and material and equipment suppliers.

    From ORS 87.021(1)

  5. 29. A notice of right to a lien protects the claimant's lien rights for work or materials provided after what date?

    Show the answer

    A. Eight days (not counting weekends and holidays) before the notice is delivered or mailed. The notice may be given at any time during the improvement, but it protects only labor, materials and equipment furnished after a date eight days, excluding Saturdays, Sundays and holidays, before delivery or mailing.

    From ORS 87.021(1)

  6. 30. Which work does NOT require the claimant to give the owner a notice of right to a lien before perfecting a lien?

    Show the answer

    B. Labor or materials on a commercial improvement. A person performing labor or supplying labor and material for a commercial improvement (a structure not used as an owner-occupied residence of four units or fewer) need not give the notice.

    From ORS 87.021(3)(b)

  7. 31. An original contractor fails to deliver the Information Notice to Owner on a residential contract above $2,000. What is the result for his lien rights?

    Show the answer

    C. He may not claim a lien on the owner's property for that contract. If an original contractor does not deliver the notice as required, he may not claim a lien on the owner's property for labor, services or materials under that contract. The board may also suspend his license or fine him up to $5,000.

    From ORS 87.093(6) and (7)

  8. 32. Who is entitled to a construction lien under ORS 87.010(1)?

    Show the answer

    D. A person who performs labor on, furnishes material for, or rents equipment used in an improvement, at the owner's or the owner's agent's instance. Anyone performing labor on, transporting or furnishing material for, or renting equipment used in construction of an improvement has a lien on it for what was furnished at the instance of the owner or the owner's construction agent.

    From ORS 87.010(1)

CCB complaints, discipline and lead paint

Complaint deadlines, who may complain, penalties, grounds for discipline and lead-based paint renovation.

  1. 33. An owner of an existing structure files a CCB complaint about completed work. By when must the CCB receive the complaint?

    Show the answer

    A. No later than one year after the contractor substantially completed the work. For an existing structure, the CCB must receive the owner's complaint no later than one year after the date the work was substantially completed by the contractor complained of.

    From ORS 701.143(2)

  2. 34. An owner of a new structure files a CCB complaint. What is the deadline?

    Show the answer

    B. The earlier of one year after first occupancy or two years after substantial completion. For a new structure, the CCB must receive the complaint no later than the earlier of one year after the structure was first occupied or two years after substantial completion.

    From ORS 701.143(1)

  3. 35. What is the maximum civil penalty the CCB may impose for each violation of ORS chapter 701 or a CCB rule, under the general penalty provision?

    Show the answer

    C. $5,000. A person who violates the chapter or a board rule may be assessed a civil penalty of not more than $5,000 for each offense.

    From ORS 701.992(1)

  4. 36. How soon must a contractor notify the CCB of a change of address or a change between exempt and nonexempt status?

    Show the answer

    D. Within 10 days after the change. A contractor must notify the board within 10 days after the change. Failure is a violation penalized under ORS 701.992(4), starting at $500 to $1,000 for a first offense.

    From ORS 701.117(1) and (2)

  5. 37. Which of these is a ground on which the CCB may discipline a licensee?

    Show the answer

    A. Hiring employees while licensed as exempt. The board may revoke, suspend, condition or refuse a license if the licensee hired employees while licensed as exempt, among other listed grounds.

    From ORS 701.098(1)(p)

  6. 38. What does a contractor's CCB surety bond pay for?

    Show the answer

    B. A complainant owed a CCB or court-ordered amount the contractor fails to pay. The bond is a promise by the surety to pay all or part of a CCB final order if the contractor fails to pay it, up to the bond amount.

    From CCB: Surety Bonds

  7. 39. Who must be certified before performing lead-based paint renovation in Oregon?

    Show the answer

    C. A contractor licensed by the CCB as a certified lead-based paint renovation contractor. A contractor may not perform lead-based paint renovation unless he is a certified lead-based paint renovation contractor licensed by the CCB. The CCB's fee schedule lists a $50 annual application and $50 annual renewal for this license.

    From ORS 701.510(2)

0 of 39 answered

Setting up your own shop

Beyond the license in Oregon, a new contracting business needs a way to schedule and bill jobs, insurance and, where the state asks for one, a bond.

Offered to tradespeople starting their own business. We may earn a share of what you pay if you buy through these links. It never changes your price, and the sellers have no say in what we publish about licensing.

Questions

Are these the real Oregon CCB Test exam questions?

No. The bodies that give the real exam keep its questions to themselves. Each question here is written for the rules or skills the exam tests, and its explanation shows the working or names the section of the regulation or code it comes from, so you learn the rule rather than one answer.

Is the practice test free?

Yes. All 39 questions and their explanations are free, with no sign-up. Your answers stay in your browser.

Checked against the rules in force on 2026-11-26. Rules and exam formats change: check the current rule and your exam provider's own information before the exam.