What the real exam is like

In most states, or in the city where you work, the journeyman exam is the step from apprentice to plumbing on your own.

  • Colorado: the Journeyworker Plumber exam, given by computer through PSI, has 100 scored questions in 240 minutes, plus up to 10 unscored questions with 30 minutes added, and you need 70 correct (70%) to pass. (Colorado State Plumbing Board Candidate Information Bulletin (PSI, updated 6/18/2026))
  • Colorado: the questions follow the 2021 IPC and the 2021 IRC (not Colorado's amendments); the test center provides both books, you may not mark them, and no formula sheet is given for the calculations section. (Colorado State Plumbing Board Candidate Information Bulletin (PSI, updated 6/18/2026))
  • Georgia: the Journeyman Plumber exam has 100 questions, taken by computer at PSI test centers in two parts of 2.5 hours each (5 hours in all), and the passing scaled score is 70. (Georgia Division of Master and Journeyman Plumbers Candidate Information Bulletin (PSI, November 2024))
  • Georgia: the Journeyman exam is the one plumbing exam where the listed references may be used, and from May 1, 2026 it is based only on the 2024 Georgia Plumbing Code (2024 IPC with Georgia amendments) and the 2024 Georgia Gas Code. (Georgia Division of Master and Journeyman Plumbers Candidate Information Bulletin (PSI, November 2024))
  • Texas: the TSBPE Journeyman Plumber exam is a 100-item written test in 120 minutes at Pearson VUE, followed by a 6-item practical in 240 minutes, and you need 70% on each part to pass. (Texas State Board of Plumbing Examiners Candidate Handbook (Pearson VUE, August 2025))
  • Texas: books and reference materials are not allowed in the exam room, and candidates study either the 2018 IPC with the 2018 International Fuel Gas Code or the 2018 UPC, plus the Plumbing License Law and Board rules. (Texas State Board of Plumbing Examiners Candidate Handbook (Pearson VUE, August 2025))

The practice test

Pick an answer to see whether it is right. Each explanation shows why, with the rule or the working behind it, so a wrong answer still teaches you something.

0 of 42 answered

Drain, waste and vent (12) · Water supply (10) · Fixtures, testing and safety (11) · Calculations (9)

Drain, waste and vent

Slope of drains, trap seals and prohibited traps, trap arms and vent rules, vent terminals, cleanouts, air admittance valves and fixture unit limits.

  1. 1. Under the 2021 IPC, what is the minimum slope for a 2-inch horizontal drainage pipe?

    Show the answer

    C. 1/4 inch per foot. Table 704.1 sets the minimum slope by pipe size: 1/4 inch per foot for 2-1/2 inches and smaller, 1/8 inch per foot for 3 to 6 inches, and 1/16 inch per foot for 8 inches and larger.

    From 2021 IPC Section 704.1 and Table 704.1

  2. 2. Under the 2021 IPC, a 4-inch horizontal drain runs to a grease interceptor. What is its minimum slope?

    Show the answer

    B. 1/4 inch per foot. A 4-inch drain normally needs only 1/8 inch per foot, but Section 704.1 requires any drainage piping upstream of a grease interceptor to slope at least 1/4 inch per foot, whatever its size.

    From 2021 IPC Section 704.1

  3. 3. Under the 2021 IPC, the liquid seal of a standard fixture trap must be:

    Show the answer

    D. At least 2 inches and at most 4 inches. Section 1002.4 requires every fixture trap to hold a liquid seal of not less than 2 inches and not more than 4 inches. Only special designs for accessible fixtures may be deeper.

    From 2021 IPC Section 1002.4

  4. 4. Under the 2021 IPC, which of these traps is prohibited?

    Show the answer

    B. An S-trap. Section 1002.3 prohibits S-traps, bell traps, crown-vented traps, traps that rely on moving parts, and drum traps (except as solids interceptors or on chemical waste). Slip joints are allowed on the trap inlet, the trap outlet and within the seal (Section 1002.2).

    From 2021 IPC Sections 1002.2 and 1002.3

  5. 5. Under the 2021 IPC, a kitchen sink has a 1-1/2-inch trap and its fixture drain slopes 1/4 inch per foot. What is the greatest developed length allowed from the trap weir to the vent fitting?

    Show the answer

    B. 6 feet. Table 909.1 limits the trap-to-vent distance by trap size: 5 feet for 1-1/4 inch, 6 feet for 1-1/2 inch and 8 feet for 2 inch (at 1/4 inch per foot), then 12 feet for 3 inch and 16 feet for 4 inch (at 1/8 inch per foot). Self-siphoning fixtures such as water closets are not limited.

    From 2021 IPC Section 909.1 and Table 909.1

  6. 6. Under the 2021 IPC, a vent may not connect to a fixture drain within what distance of the trap weir?

    Show the answer

    A. Two pipe diameters. Section 909.3 bars a vent within two pipe diameters of the trap weir. A vent that close is a crown vent, and Section 1002.3 lists crown-vented traps as prohibited.

    From 2021 IPC Section 909.3

  7. 7. Under the 2021 IPC, a dry vent must rise vertically to at least what height above the flood level rim of the highest trap or trapped fixture it serves?

    Show the answer

    D. 6 inches. Section 905.4 requires every dry vent to rise vertically to at least 6 inches above the flood level rim of the highest trap or trapped fixture being vented. Section 905.5 likewise keeps horizontal branch, relief and loop vents at least 6 inches above the flood level rim of the highest fixture served.

    From 2021 IPC Sections 905.4 and 905.5

  8. 8. Under the 2021 IPC, an open vent terminal is 6 feet horizontally from an openable window. How far above the top of the window must it be?

    Show the answer

    C. 3 feet. Section 903.5 keeps vent terminals from directly beneath a door, openable window or air intake, and a terminal within 10 feet horizontally of such an opening must be at least 3 feet above the top of it.

    From 2021 IPC Section 903.5

  9. 9. Under the 2021 IPC, a building drain makes a 90-degree change of horizontal direction. What is required?

    Show the answer

    B. A cleanout at the change of direction. Section 708.1.4 requires a cleanout at any change of horizontal direction greater than 45 degrees in a horizontal drain, building drain or building sewer. Where several such changes occur within 40 feet of developed length, the cleanout at the first one serves them all.

    From 2021 IPC Section 708.1.4

  10. 10. Under the 2021 IPC, what is the most drainage fixture units (dfu) a 3-inch horizontal fixture branch may carry?

    Show the answer

    D. 20 dfu. Table 710.1(2) allows 20 dfu on a 3-inch horizontal fixture branch. The 48 dfu figure is for a 3-inch stack of three branch intervals or less, and 42 dfu is a 3-inch building drain at 1/4 inch per foot in Table 710.1(1).

    From 2021 IPC Section 710.1 and Tables 710.1(1) and 710.1(2)

  11. 11. Under the 2021 IPC, an individual or branch-type air admittance valve must be installed at least how far above the horizontal branch drain or fixture drain it vents?

    Show the answer

    A. 4 inches. Section 918.4 sets individual and branch-type air admittance valves at least 4 inches above the drain being vented, and stack-type valves at least 6 inches above the flood level rim of the highest fixture served. Every valve must also be at least 6 inches above insulation and accessible.

    From 2021 IPC Section 918.4

  12. 12. Under the 2021 IPC, an individual vent serves a 3-inch drain and has a developed length of 50 feet. What is its minimum diameter?

    Show the answer

    C. 2 inches. Section 906.2 makes an individual vent at least half the required drain diameter (1-1/2 inches for a 3-inch drain) and never under 1-1/4 inches. A vent longer than 40 feet of developed length is increased one nominal size for its whole length, so 1-1/2 inches becomes 2 inches.

    From 2021 IPC Section 906.2

Water supply

Service and distribution basics, pressure, pipe materials, water heaters and relief valves, backflow protection and air gaps.

  1. 13. Under the 2021 IPC, above what static pressure inside a building must a pressure-reducing valve be installed?

    Show the answer

    A. 80 psi. Section 604.8 requires an approved pressure-reducing valve with a strainer where the static pressure in the building exceeds 80 psi, set to keep the distribution piping at 80 psi static or less. Lines serving only sill cocks and outside hydrants are exempt.

    From 2021 IPC Section 604.8

  2. 14. Under the 2021 IPC, what is the smallest diameter allowed for a water service pipe?

    Show the answer

    D. 3/4 inch. Section 603.1 requires the water service to be sized for the flows and pressures the building needs, and in no case smaller than 3/4 inch in diameter.

    From 2021 IPC Section 603.1

  3. 15. Under the 2021 IPC, a water service runs beside a building sewer whose material is not listed in Table 702.2. With no crossing and the water line not raised above the sewer, how far apart horizontally must they be?

    Show the answer

    C. 5 feet. Section 603.2 requires at least 5 feet of undisturbed or compacted earth between them in that case. The separation is not needed where the bottom of the water service is at least 12 inches above the top of the sewer, or where the water service is sleeved 5 feet each side of a crossing.

    From 2021 IPC Section 603.2

  4. 16. Under the 2021 IPC, what is the highest temperature setting allowed for the temperature relief valve on a storage water heater?

    Show the answer

    D. 210 degrees F. Section 504.5 limits the temperature setting to 210 degrees F and the pressure setting to the tank's rated working pressure or 150 psi, whichever is less. Each valve's relieving capacity must at least equal the heater's heat input.

    From 2021 IPC Section 504.5

  5. 17. Under the 2021 IPC, which of these is allowed for the discharge piping from a water heater's temperature and pressure relief valve?

    Show the answer

    D. Discharging into the pan that serves the water heater. Section 504.6 allows the discharge to end at the floor, the water heater pan, a waste receptor or the outdoors. The pipe must not have a threaded end, valves or tee fittings, must serve one relief device only, must not be trapped and must flow by gravity.

    From 2021 IPC Section 504.6

  6. 18. Under the 2021 IPC, the cold water to a storage water heater passes through a pressure-reducing valve. What must be added?

    Show the answer

    C. A thermal expansion control device on the cold supply, downstream of the reducing valve. Section 607.3 requires a thermal expansion control device on the heater's cold supply, downstream of every check valve, pressure-reducing valve and backflow preventer. Section 504.4 forbids using the relief valve to control thermal expansion.

    From 2021 IPC Sections 607.3 and 504.4

  7. 19. Under the 2021 IPC, a sink faucet has an effective opening of 3/4 inch and is not close to a wall. What is the minimum air gap between its outlet and the flood level rim?

    Show the answer

    B. 1-1/2 inches. Table 608.16.1 requires 1-1/2 inches for sinks and other fixtures with effective openings up to 3/4 inch when away from a wall, and 2-1/2 inches when close to a wall. The gap is measured vertically from the lowest end of the outlet to the flood level rim (Section 608.14.1).

    From 2021 IPC Section 608.16.1 and Table 608.16.1

  8. 20. Under the 2021 IPC, the critical level of a pressure vacuum breaker assembly must be at least how far above all downstream piping and outlets?

    Show the answer

    A. 12 inches. Section 608.14.5 sets pressure vacuum breaker and spill-resistant vacuum breaker assemblies with their critical level at least 12 inches above all downstream piping and outlets. An atmospheric or pressure-type vacuum breaker protecting a fixture opening is set at least 6 inches above the flood level rim (Section 608.16.4).

    From 2021 IPC Section 608.14.5

  9. 21. Under the 2021 IPC, a lawn irrigation system injects fertilizer into the water. What backflow protection must the potable supply have?

    Show the answer

    D. A reduced pressure principle backflow prevention assembly. Section 608.17.5 allows an atmospheric vacuum breaker, a pressure vacuum breaker assembly or a reduced pressure principle assembly on irrigation, but where chemicals are introduced it requires a reduced pressure principle backflow prevention assembly. No valves may be installed downstream of an atmospheric vacuum breaker.

    From 2021 IPC Section 608.17.5

  10. 22. Under the 2021 IPC, which of these materials is listed for water service pipe but not for water distribution pipe inside the building?

    Show the answer

    D. PVC plastic pipe. Table 605.3 lists PVC (as well as ABS and PE) for water service, but Table 605.4 does not list it for water distribution. Section 605.3 has service piping not certified for distribution end at or before the full open valve at the entrance to the structure.

    From 2021 IPC Sections 605.3 and 605.4, Tables 605.3 and 605.4

Fixtures, testing and safety

Fixture setting and shower rules, indirect waste and standpipes, testing the DWV and water systems, pipe support and trench safety.

  1. 23. Under the 2021 IPC, how close may the center of a water closet be to a side wall or partition?

    Show the answer

    A. 15 inches. Section 405.3.1 keeps the center of a water closet, urinal, lavatory or bidet at least 15 inches from any side wall, partition or vanity. Adjacent water closets, urinals or bidets with no partition between them must be at least 30 inches center to center, and at least 21 inches of clear space is required in front.

    From 2021 IPC Section 405.3.1

  2. 24. Under the 2021 IPC, what are the minimum least dimension and minimum interior area of a standard shower compartment?

    Show the answer

    B. 30 inches and 900 square inches. Section 421.4 requires at least 900 square inches of interior cross-sectional area and at least 30 inches in the least dimension. As an exception, a compartment as narrow as 25 inches is allowed if it has at least 1,300 square inches of area.

    From 2021 IPC Section 421.4

  3. 25. Under the 2021 IPC, an individual shower valve must have a limit stop that keeps the water from exceeding what temperature?

    Show the answer

    A. 120 degrees F. Section 412.3 requires individual shower and tub-shower valves to be balanced-pressure, thermostatic or combination valves installed at the point of use, with the maximum setting field adjusted so the water does not exceed 120 degrees F. The 110 degrees F figure is the setting for a tempered water limiting device (Section 607.1.2).

    From 2021 IPC Section 412.3

  4. 26. Under the 2021 IPC, a clothes washer standpipe must extend how far above its trap weir?

    Show the answer

    B. 18 to 42 inches. Section 802.4.3 requires each standpipe to be individually trapped and to rise not less than 18 inches and not more than 42 inches above the trap weir. Section 406.2 makes the washer trap and fixture drain at least 2 inches and connects them to a 3-inch or larger branch or stack.

    From 2021 IPC Sections 802.4.3 and 406.2

  5. 27. Under the 2021 IPC, a sterilizer discharges potable clear-water waste through a 1-inch indirect waste pipe into a floor sink. What is required?

    Show the answer

    B. An air gap of at least 2 inches above the flood level rim. Section 802.1.3 requires potable clear-water waste from equipment such as sterilizers and relief valves to discharge through an air gap. Section 802.3.1 makes the air gap at least twice the effective opening of the indirect waste pipe, so 2 inches for a 1-inch pipe.

    From 2021 IPC Sections 802.1.3 and 802.3.1

  6. 28. Under the 2021 IPC, which is required for a residential dishwasher waste line?

    Show the answer

    A. It rises and is fastened to the underside of the sink rim or countertop. Section 409.4 has the waste connect to a wye branch on the kitchen sink tailpiece, to the dishwasher inlet of a food waste disposer, or through an air break to a standpipe, and the waste line must rise and be secured to the underside of the sink rim or countertop.

    From 2021 IPC Section 409.4

  7. 29. Under the 2021 IPC, a section of drainage and vent piping is given a water test. What is the minimum test?

    Show the answer

    C. A 10-foot head of water held 15 minutes. Section 312.2 requires each section to be filled to at least a 10-foot head of water and held at least 15 minutes, with the system tight at all points. When testing in sections, at least the upper 10 feet of the previous section is retested.

    From 2021 IPC Section 312.2

  8. 30. Under the 2021 IPC, a cast-iron drainage and vent system is tested with air. What is the minimum test?

    Show the answer

    A. 5 psi held 15 minutes. Section 312.3 requires a uniform 5 psi (or enough to balance a 10-inch column of mercury) held at least 15 minutes, and it forbids testing plastic piping with air. The 50 psi air test belongs to water supply piping other than plastic (Section 312.5).

    From 2021 IPC Section 312.3

  9. 31. Under the 2021 IPC, how must a new PEX water distribution system be tested?

    Show the answer

    B. With water at not less than the system working pressure for 15 minutes. Section 312.5 requires the water supply system to be proved tight under water at not less than its working pressure for at least 15 minutes, using water from a potable source. The air test of at least 50 psi is allowed only for piping other than plastic.

    From 2021 IPC Section 312.5

  10. 32. Under the 2021 IPC, what is the maximum horizontal spacing of hangers for PVC pipe?

    Show the answer

    B. 4 feet. Table 308.5 sets PVC and ABS at 4 feet horizontally and 10 feet vertically, with a mid-story guide for sizes 2 inches and smaller. For comparison, copper tubing 1-1/4 inches and smaller is 6 feet and cast-iron pipe is 5 feet (10 feet with 10-foot lengths).

    From 2021 IPC Section 308.5 and Table 308.5

  11. 33. Under OSHA's excavation rules (29 CFR 1926), a trench in ordinary soil is 5 feet deep. What must protect workers in it?

    Show the answer

    A. A protective system such as sloping, benching, shoring or a trench shield. 29 CFR 1926.652(a)(1) requires an adequate protective system for every worker in an excavation unless it is entirely in stable rock, or less than 5 feet deep with no sign of a cave-in found by a competent person. A ladder or other way out within 25 feet of lateral travel is a separate rule for trenches 4 feet or deeper (1926.651(c)(2)).

    From 29 CFR 1926.652(a)(1) and 1926.651(c)(2)

Calculations

Slope and fall, pressure from head and elevation, pipe volume, fixture unit totals and code distances worked out from pipe size.

  1. 34. Under the 2021 IPC, a 3-inch building drain runs 60 feet at the minimum slope allowed. How much total fall does it have?

    Show the answer

    D. 7-1/2 inches. Table 704.1 sets 1/8 inch per foot as the minimum for 3- to 6-inch drains. Fall equals slope times run: 1/8 inch x 60 feet = 7.5 inches. (At 1/4 inch per foot it would be 15 inches.)

    From 2021 IPC Section 704.1 and Table 704.1

  2. 35. Under the 2021 IPC, the total fall of a fixture drain may not exceed its diameter. A 2-inch fixture drain slopes 1/4 inch per foot. What is the longest it can run before the fall reaches the limit?

    Show the answer

    C. 8 feet. Section 909.2 caps the fall at the pipe diameter, 2 inches here. Length = fall / slope = 2 inches / 0.25 inch per foot = 8 feet, which matches the 8-foot trap-to-vent limit for a 2-inch trap in Table 909.1.

    From 2021 IPC Section 909.2 and Table 909.1

  3. 36. A DWV water test puts a 10-foot head of water on the lowest joint of a section. Using 0.433 psi per foot of head, what pressure does that joint see?

    Show the answer

    B. 4.33 psi. Pressure from a column of water is 0.433 psi per foot of height, the factor the 2021 IPC uses in Appendix E. 10 feet x 0.433 psi per foot = 4.33 psi. Section 312.2 requires at least this 10-foot head for a DWV water test.

    From 2021 IPC Appendix E Section E103.2.2 (0.433 psi per foot) and Section 312.2

  4. 37. The water main holds 60 psi static. The highest fixture outlet is 35 feet above the main. Ignoring friction, about what static pressure remains at that outlet?

    Show the answer

    A. 44.8 psi. Elevation costs 0.433 psi per foot of rise (2021 IPC Appendix E). 35 feet x 0.433 = 15.2 psi lost, and 60 - 15.2 = 44.8 psi. Water loses pressure as it rises, so the loss is subtracted, never added.

    From 2021 IPC Appendix E Section E103.2.2

  5. 38. About how many gallons of water fill 100 feet of pipe with an inside diameter of 4 inches?

    Show the answer

    C. 65.3 gallons. Volume = area x length. Area = 3.1416 x (2 inches)^2 = 12.57 square inches; length = 100 feet x 12 = 1,200 inches; volume = 15,080 cubic inches. A US gallon is 231 cubic inches, so 15,080 / 231 = 65.3 gallons.

    From NIST Handbook 44 (2026), Appendix C: 1 gallon = 231 cubic inches

  6. 39. Under the 2021 IPC, a house drain serves two bathroom groups with 1.6 gpf water closets, a domestic kitchen sink, a residential clothes washer and a laundry tray. What is the total drainage fixture unit load?

    Show the answer

    D. 16 dfu. Table 709.1 gives 5 dfu per bathroom group with a 1.6 gpf water closet and 2 dfu each for a domestic kitchen sink, a residential clothes washer and a laundry tray. 2 x 5 + 2 + 2 + 2 = 16 dfu.

    From 2021 IPC Section 709.1 and Table 709.1

  7. 40. Under the 2021 IPC, a building drain at 1/4 inch per foot carries 18 dfu, including water closets. What is its minimum size?

    Show the answer

    C. 3 inches. Table 710.1(1) lets a 2-inch building drain at 1/4 inch per foot carry 21 dfu, so the load alone would allow 2 inches. But footnote a of that table sets 3 inches as the minimum size for any building drain serving a water closet.

    From 2021 IPC Table 710.1(1) and footnote a

  8. 41. Under the 2021 IPC, a horizontal branch connects downstream of the base of a 4-inch drainage stack. What is the minimum distance from the stack to that connection?

    Show the answer

    A. 40 inches. Section 704.3 requires horizontal branches to connect at least 10 stack diameters downstream of the base of a stack (and of a horizontal stack offset). 10 x 4 inches = 40 inches.

    From 2021 IPC Section 704.3

  9. 42. Under the 2021 IPC, a 3/4-inch relief valve discharge pipe ends over the floor. Within what height range above the floor must its end be?

    Show the answer

    D. Between 1-1/2 inches and 6 inches. Section 504.6 item 10 ends the discharge pipe not more than 6 inches above the floor or receptor rim and not less than two times the pipe diameter above it. 2 x 3/4 inch = 1-1/2 inches, so the end must sit between 1-1/2 and 6 inches.

    From 2021 IPC Section 504.6, item 10

0 of 42 answered

Ready for the real exam?

Offered to people preparing for the journeyman plumber exam. We may earn a share of what you pay if you buy through these links. It never changes your price, and the sellers have no say in the jobs we list. As an Amazon Associate I earn from qualifying purchases.

Questions

Are these the real Journeyman Plumber exam questions?

No. The bodies that give the real exam keep its questions to themselves. Each question here is written for the rules or skills the exam tests, and its explanation shows the working or names the section of the regulation or code it comes from, so you learn the rule rather than one answer.

Is the practice test free?

Yes. All 42 questions and their explanations are free, with no sign-up. Your answers stay in your browser.

Checked against the rules in force on 2026-11-26. Rules and exam formats change: check the current rule and your exam provider's own information before the exam.