Skip to content

Free practice test

North Carolina General Contractor Exam Practice Test

Practice for the business and law part of North Carolina's general contractor exams, on what is North Carolina's own: the license limits and the qualifier, liens and the lien agent, prompt payment and retainage, and workers' comp. Pick an answer to see whether it is right and the statute behind it.

32
practice questions
each with its answer explained
5
sections
Licensing, Getting licensed, Liens on real property, Payment to subcontractors and retainage, Workers' comp and permits
70%
to pass the real exam
as its official rules state

What the real exam is like

Passing the board's exams is what the North Carolina Licensing Board for General Contractors asks of a qualifier before it issues a license.

  • The qualifier (an owner or responsible managing employee) must pass the Board's examination, which covers the qualifier's knowledge of contractor responsibilities, North Carolina contractor, construction and lien law, estimating, and the Sedimentation Pollution Control Act. (N.C. Gen. Stat. 87-10(b))
  • The Business and Law examination has 40 questions and 90 minutes, and a score of at least 70 percent is required to pass (the Board's rule sets a score of at least 70). (PSI Candidate Information Bulletin, North Carolina Licensing Board for General Contractors, Business and Law)
  • The Business and Law exam is open book: candidates bring the NASCLA Contractor's Guide to Business, Law and Project Management, North Carolina General Contractors Edition (10th Edition), bound, with permanent tabs only and no notes written in it. (PSI Candidate Information Bulletin, North Carolina Licensing Board for General Contractors, Business and Law reference list)
  • The 40 scored items split as Licensing 21, Liens and Bonds 8, One Call 5, Erosion and Sedimentation Control 3 and Subcontractor's Pay Requirements 3. (PSI Candidate Information Bulletin, Business and Law content outline)
  • After the Board approves the application it sends an eligibility letter valid for 120 days for one exam, and the candidate then schedules the computer-based exam with PSI. (PSI Candidate Information Bulletin, Guidelines for Licensing and scheduling)

The practice test

Pick an answer to see whether it is right. Each explanation shows why, with the rule or the working behind it, so a wrong answer still teaches you something.

0 of 32 answered

Licensing (7) · Getting licensed (6) · Liens on real property (7) · Payment to subcontractors and retainage (6) · Workers' comp and permits (6)

Licensing

When a North Carolina general contractor license is required, who may hold it, and what the Board can do about violations.

  1. 1. Under North Carolina law, a general contractor must hold a license to undertake a project when its cost is at least what amount?

    Show the answer

    B. $40,000. G.S. 87-1(a) defines a general contractor as one who bids on or builds any building, highway, utility, grading or structure where the cost is $40,000 or more.

    From N.C. Gen. Stat. 87-1(a)

  2. 2. An intermediate license holder may act as general contractor on a single project valued up to what limit?

    Show the answer

    C. $1,500,000, excluding the cost of land and ancillary costs to improve the land. G.S. 87-10(a1): intermediate license up to $1,500,000 per project; limited up to $750,000; unlimited has no limit. Land and ancillary land-improvement costs are excluded.

    From N.C. Gen. Stat. 87-10(a1)

  3. 3. A contractor holds a limited license. What is the largest single project (excluding land cost) the contractor may take as general contractor?

    Show the answer

    D. $750,000. G.S. 87-10(a1) sets the limited license at a single project value of up to $750,000, excluding land and ancillary land-improvement costs.

    From N.C. Gen. Stat. 87-10(a1)

  4. 4. The qualifier of a licensed company leaves the company. What happens to the license?

    Show the answer

    B. It stays valid for 90 days, but the licensee may not bid on or undertake additional contracts in that time. G.S. 87-10(c1): the license stays in force for 90 days after the qualifier ceases to be connected with the licensee, but during that period the licensee cannot bid on or take additional contracts. After 90 days it is invalidated until reinstated.

    From N.C. Gen. Stat. 87-10(c1)

  5. 5. A general contractor license expires on the first day of January. What is the effect if it is not renewed?

    Show the answer

    C. It becomes invalid 60 days after January 1 unless renewed. G.S. 87-10(e): a license expires on the first day of January following its issuance or renewal and becomes invalid 60 days from that date unless renewed, with a $10 late payment for each month or part after January.

    From N.C. Gen. Stat. 87-10(e)

  6. 6. A building contractor license renewal requires eight hours of continuing education a year. How are the eight hours divided?

    Show the answer

    D. Two hours are a mandatory Board course and six hours are electives. G.S. 87-10.2(b): of the eight annual hours, two are a mandatory course approved by the Board and six are electives. Up to four elective hours may be carried forward.

    From N.C. Gen. Stat. 87-10.2(b)

  7. 7. What is the criminal penalty under G.S. 87-13 for bidding on or contracting for a project that requires a general contractor license without being licensed?

    Show the answer

    A. A Class 2 misdemeanor. G.S. 87-13 makes unlicensed contracting, using another's certificate, or using an expired or revoked license a Class 2 misdemeanor. The Board can also seek an injunction under G.S. 87-13.1.

    From N.C. Gen. Stat. 87-13

Getting licensed

Who may apply, what the exam covers and passes at, and the financial showing the Board rules require for each license.

  1. 8. An owner builds a house on her own land for her family to live in and is exempt from licensing. After completion, how long must the house be occupied solely by her family or it is presumed she did not intend it for that use?

    Show the answer

    C. 12 months. G.S. 87-1(b)(2): if the building is not occupied solely by the owner and family for at least 12 months after completion, it is presumed the owner did not intend it solely for their own occupancy.

    From N.C. Gen. Stat. 87-1(b)(2)

  2. 9. The Board's rules set what minimum score to pass the licensing examination?

    Show the answer

    D. 70. 21 NCAC 12A .0404: persons taking the examination must receive a score of at least 70 to pass.

    From 21 NCAC 12A .0404 (Board's 2026 Laws and Regulations)

  3. 10. An applicant for an unlimited license shows financial responsibility by current assets exceeding current liabilities by at least what amount, shown in an agreed-upon procedures report or audited statement?

    Show the answer

    A. $150,000. 21 NCAC 12A .0204(d): unlimited license requires working capital of at least $150,000. Intermediate requires $75,000 and limited requires $17,000 working capital or $80,000 net worth.

    From 21 NCAC 12A .0204(d) (Board's 2026 Laws and Regulations)

  4. 11. What working capital (current assets minus current liabilities) must an intermediate license applicant show?

    Show the answer

    B. $75,000. 21 NCAC 12A .0204(c) requires current assets to exceed current liabilities by at least $75,000, shown by an agreed-upon procedures report or audited statement.

    From 21 NCAC 12A .0204(c) (Board's 2026 Laws and Regulations)

  5. 12. In place of showing working capital, an applicant for an intermediate license may maintain a continuous surety bond of what amount?

    Show the answer

    D. $500,000. 21 NCAC 12A .0204(e) sets the bond amounts at $175,000 for a limited license, $500,000 for an intermediate license and $1,000,000 for an unlimited license.

    From 21 NCAC 12A .0204(e) (Board's 2026 Laws and Regulations)

  6. 13. A company wants to be licensed as both a building contractor and a highway contractor. How many examinations must be taken?

    Show the answer

    A. Two examinations, one for each classification. 21 NCAC 12A .0403: an applicant must take one different examination for each classification of general contracting for which the applicant seeks licensure.

    From 21 NCAC 12A .0403 (Board's 2026 Laws and Regulations)

Liens on real property

Chapter 44A Article 2 Part 1: who has lien rights, the lien agent, and the deadlines to file and enforce.

  1. 14. What is the deadline to file a claim of lien on real property in North Carolina?

    Show the answer

    B. No later than 120 days after the last furnishing of labor or materials at the site. G.S. 44A-12(b): a claim of lien may be filed after the obligation matures, but not later than 120 days after the claimant last furnished labor or materials at the site.

    From N.C. Gen. Stat. 44A-12(b)

  2. 15. After a claim of lien is filed, an action to enforce it must be commenced within what time?

    Show the answer

    C. No later than 180 days after the last furnishing of labor or materials at the site. G.S. 44A-13(a): no action to enforce a claim of lien on real property may be commenced later than 180 days after the last furnishing of labor or materials at the site.

    From N.C. Gen. Stat. 44A-13(a)

  3. 16. Where is a claim of lien on real property filed?

    Show the answer

    A. The clerk of superior court in each county where the property is located. G.S. 44A-12(a): claims of lien must be filed with the clerk of superior court in each county where the real property is located.

    From N.C. Gen. Stat. 44A-12(a)

  4. 17. On a project that requires a lien agent, a potential lien claimant keeps full lien rights against a previously recorded mortgage if the lien agent receives its Notice to Lien Agent no later than when?

    Show the answer

    B. No later than 15 days after the first furnishing of labor or materials. G.S. 44A-11.2(m)(1) (and (l)(1)): the lien agent must receive the Notice to Lien Agent no later than 15 days after the claimant first furnishes labor or materials. Receipt before the mortgage is recorded also works under (m)(2).

    From N.C. Gen. Stat. 44A-11.2(l), (m)

  5. 18. A properly perfected claim of lien on real property takes effect as of what time?

    Show the answer

    C. From the time of the first furnishing of labor or materials at the site by the claimant. G.S. 44A-10: the claim of lien relates to and takes effect from the time of the first furnishing of labor or materials at the site by the person claiming it, once perfected under 44A-11.

    From N.C. Gen. Stat. 44A-10

  6. 19. A bid package says a contractor must waive the right to file a claim of lien as a condition of being awarded the contract. What is the effect under G.S. 44A-12(f)?

    Show the answer

    D. It is against public policy and unenforceable. G.S. 44A-12(f): an agreement to waive lien rights in anticipation of and in consideration for the award of a contract is against public policy and unenforceable. Subordination or release of a lien is not prohibited.

    From N.C. Gen. Stat. 44A-12(f)

  7. 20. A lien claimant finds a mistake in the amount on a filed claim of lien on real property. What does G.S. 44A-12(d) allow?

    Show the answer

    B. It may not be amended, but may be cancelled and a new claim substituted within the original filing time. G.S. 44A-12(d): a claim of lien may not be amended, but may be cancelled and a new claim of lien substituted within the time allowed for the original filing.

    From N.C. Gen. Stat. 44A-12(d)

Payment to subcontractors and retainage

Chapter 22C and G.S. 143-134.1 on how fast subcontractors must be paid and how much public owners may hold back.

  1. 21. Under G.S. 22C-3, a contractor who has been paid must pay a subcontractor that performed under its contract the full amount received for that work by when?

    Show the answer

    C. Within 7 days of receiving each periodic or final payment. G.S. 22C-3: the contractor must pay the subcontractor within seven days of receipt of each periodic or final payment the full amount received for the subcontractor's work and materials.

    From N.C. Gen. Stat. 22C-3

  2. 22. A subcontract says the contractor pays the subcontractor only if and when the owner pays the contractor. Under G.S. 22C-2, what is the result?

    Show the answer

    D. It is unenforceable; the owner's payment to the contractor is not a condition precedent to paying the subcontractor. G.S. 22C-2: payment by the owner to a contractor is not a condition precedent for payment to a subcontractor, and an agreement to the contrary is unenforceable.

    From N.C. Gen. Stat. 22C-2

  3. 23. On a public construction contract, the balance due the prime contractor must be paid in full within how many days after acceptance, certification of completion, or occupancy, and when does interest start?

    Show the answer

    A. 45 days; interest at 1% per month starting on the 46th day. G.S. 143-134.1(a): final payment is due within 45 days; if delayed more than 45 days, interest runs from the 46th day at one percent per month or fraction thereof unless a lower rate is agreed.

    From N.C. Gen. Stat. 143-134.1(a)

  4. 24. On a public project, the prime contractor receives a payment and does not pay the subcontractor within seven days. What interest applies?

    Show the answer

    C. 1% per month, beginning on the eighth day. G.S. 143-134.1(b): if payment to the subcontractor is delayed more than seven days after the prime contractor's receipt, the prime contractor owes interest beginning on the eighth day at 1% per month or fraction thereof.

    From N.C. Gen. Stat. 143-134.1(b)

  5. 25. What does G.S. 143-134.1(b1) say about retainage on public construction contracts with total project costs under $150,000?

    Show the answer

    D. No retainage may be held on a public contract with total project costs under $150,000. G.S. 143-134.1(b1): no retainage is allowed where total project costs are less than $150,000. At $150,000 or more the owner may not retain more than 5% of any periodic payment.

    From N.C. Gen. Stat. 143-134.1(b1)

  6. 26. Under G.S. 143-134.1(b2), which of these is one of the listed early-finishing trades that may be paid in full, with retainage reduced to 0.5%, once it reaches 100% completion before the project is 50% complete?

    Show the answer

    A. Structural steel. G.S. 143-134.1(b2) lists structural steel, piling, caisson and demolition as early-finishing trades, subject to the satisfactory performance of the contractor and architect or engineer approval of the work.

    From N.C. Gen. Stat. 143-134.1(b2)

Workers' comp and permits

Chapter 97 rules for contractors who sublet work and what a permit applicant must prove under G.S. 87-14.

  1. 27. Under G.S. 97-2, private employment is generally covered by the Workers' Compensation Act when an employer regularly employs at least how many employees in the same business or establishment?

    Show the answer

    B. Three or more employees regularly employed in the same business or establishment. G.S. 97-2(1) includes private employments in which three or more employees are regularly employed in the same business or establishment (with exceptions such as radiation work and certain agriculture).

    From N.C. Gen. Stat. 97-2(1)

  2. 28. A general contractor sublets work without getting a certificate of the subcontractor's workers' compensation coverage. A worker of the one-person-plus-helper subcontractor (fewer than three employees) is hurt on the job. What does G.S. 97-19 say?

    Show the answer

    D. The general contractor is liable as if the subcontractor were covered, even if the subcontractor has fewer than three employees. G.S. 97-19: a principal contractor who sublets without obtaining the required certificate is liable irrespective of whether the subcontractor has fewer than three employees, to the same extent as the subcontractor would be if subject to the Act.

    From N.C. Gen. Stat. 97-19

  3. 29. To avoid liability to a subcontractor's employees under G.S. 97-19, what must a contractor obtain before subletting?

    Show the answer

    A. A certificate from the subcontractor's workers' compensation insurance carrier (or a certificate of compliance for a self-insured sub) stating it has complied with G.S. 97-93. G.S. 97-19: obtaining the certificate issued by the carrier (or by the Department of Insurance for a self-insured subcontractor) stating compliance with G.S. 97-93 for a specified term protects the contractor for that term.

    From N.C. Gen. Stat. 97-19

  4. 30. Besides proof of licensure or an exemption, what must an applicant for a building permit on a project costing $40,000 or more show the local inspection authority under G.S. 87-14(a)?

    Show the answer

    B. Proof that the applicant has workers' compensation insurance in effect as required by Chapter 97. G.S. 87-14(a)(2) requires the applicant to furnish proof that workers' compensation insurance is in effect as required by Chapter 97, in addition to proof of licensure or exemption.

    From N.C. Gen. Stat. 87-14(a)(2)

  5. 31. An owner claims the owner-occupant exemption when applying for a building permit. The verified affidavit under G.S. 87-14(a)(1) must state what about the construction?

    Show the answer

    C. That the applicant will personally superintend and manage all the construction and not delegate it to anyone not licensed. G.S. 87-14(a)(1)b: the owner attests that the owner will personally superintend and manage all aspects of the construction and not delegate that duty to anyone not licensed under Article 1. The owner must also be present for inspections unless an architect sealed the plans.

    From N.C. Gen. Stat. 87-14(a)(1)

  6. 32. A building permit application for improvements of $40,000 or more must include the owner's designated lien agent information under G.S. 87-14(a1), except for which project?

    Show the answer

    A. A $40,000 renovation of an existing single-family house the owner lives in. G.S. 87-14(a1) exempts improvements to an existing single-family residential dwelling unit that the owner occupies as a residence (and accessory buildings incidental to it).

    From N.C. Gen. Stat. 87-14(a1)

0 of 32 answered

Setting up your own shop

Beyond the license in North Carolina, a new contracting business needs a way to schedule and bill jobs, insurance and, where the state asks for one, a bond.

Offered to tradespeople starting their own business. We may earn a share of what you pay if you buy through these links. It never changes your price, and the sellers have no say in what we publish about licensing.

Questions

Are these the real North Carolina General Contractor Exam exam questions?

No. The bodies that give the real exam keep its questions to themselves. Each question here is written for the rules or skills the exam tests, and its explanation shows the working or names the section of the regulation or code it comes from, so you learn the rule rather than one answer.

Is the practice test free?

Yes. All 32 questions and their explanations are free, with no sign-up. Your answers stay in your browser.

Checked against the rules in force on 2026-11-26. Rules and exam formats change: check the current rule and your exam provider's own information before the exam.