Free practice test
Practice for the Law and Business exam every California contractor license applicant takes beside the trade exam, in the sections CSLB's own study guide tests. Pick an answer to see whether it is right and the code section behind it.
Passing it, with the trade exam for your classification, is what CSLB asks of the qualifier before it issues a California contractor license.
Pick an answer to see whether it is right. Each explanation shows why, with the rule or the working behind it, so a wrong answer still teaches you something.
Business organization and licensing (7) · Business finances (7) · Employment requirements (9) · Insurance and liens (6) · Contract requirements and execution (10) · Public works (3) · Safety (6)
Who needs a California contractor license, the qualifier and its duties, bonds and LLC insurance, license numbers in ads and on vehicles, reporting changes and unlicensed contracting penalties.
1. In 2026 an unlicensed handyman works alone and does not advertise as a contractor. Under the minor-work exemption in Business and Professions Code 7048, which job may he legally take?
C. Repairing a gate for $950 in labor and materials, with no building permit needed. The exemption covers only a job whose aggregate contract price for labor, materials and all other items is less than $1,000 and that needs no building permit. It is lost if the work is divided into contracts under $1,000 to evade the law, or if the person advertises as a contractor or employs anyone to help with the work.
From Business and Professions Code 7048(a) to (c) (as amended effective January 1, 2026)
2. A corporation's license is qualified by its responsible managing officer (RMO), who owns 5 percent of the corporation's voting stock. Which bonds must be on file to keep the license active?
A. A $25,000 contractor's bond plus a separate $25,000 qualifying individual's bond. BPC 7071.6 requires a $25,000 contractor's bond for an active license. Under BPC 7071.9 a qualifier who is not the proprietor or a general partner also files a $25,000 qualifying individual's bond, which may not be combined with the contractor's bond; an RMO is excused only by owning 10 percent or more of the voting stock, and 5 percent is not enough.
From Business and Professions Code 7071.6(a) and 7071.9(a) and (c)
3. A qualifier meets one of the conditions in BPC 7068.1 for qualifying more than one firm, such as at least 20 percent common ownership. Even so, for how many firms may that person act as the qualifier in any one-year period?
B. Three. The qualifier is responsible for supervision and control of the firm's construction operations, so a person may qualify an additional firm only with at least 20 percent common ownership, a subsidiary or joint venture, or the same majority of partners, officers or managers. Even then, BPC 7068.1(b) caps it at three firms in any one-year period.
From Business and Professions Code 7068.1(a) and (b)
4. A limited liability company's contractor license lists 8 persons on its personnel of record. What is the least aggregate limit of liability insurance the LLC must carry?
C. $1,300,000. An LLC with five or fewer persons listed needs at least $1,000,000 in aggregate liability coverage, plus $100,000 for each additional person listed, up to a $5,000,000 cap. Eight persons is three more than five, so $1,000,000 + 3 x $100,000 = $1,300,000. An active LLC license also needs a $100,000 worker bond on top of the $25,000 contractor's bond (BPC 7071.6.5).
From Business and Professions Code 7071.19(b); CSLB, Get Licensed to Build (2025), Issuing a License, Q1
5. A licensed C-36 plumbing contractor pays commercial registration on its service trucks. What must appear on each truck?
A. Its name, permanent business address and license number on each side, in letters and numerals at least 1.5 inches high. BPC 7029.5 requires C-36 plumbing, C-45 sign and C-57 well-drilling contractors to show their name, permanent business address and license number on each side of each commercially registered vehicle, in characters at least 1.5 inches high. Separately, BPC 7030.5 requires every licensee to put its license number in all construction contracts, subcontracts, calls for bid and all forms of advertising.
From Business and Professions Code 7029.5 (with 7030.5)
6. The responsible managing employee who qualifies a license quits on April 1. Under BPC 7068.2, what is required?
C. The licensee or qualifier must notify the registrar in writing within 90 days, and the licensee has 90 days from the disassociation to replace the qualifier or the license is automatically suspended. When an RMO, RME, responsible managing member or manager disassociates, the licensee or the qualifier must notify the registrar in writing within 90 days, and the licensee has 90 days from the disassociation to replace the qualifier; if not, the license is automatically suspended or the classification removed. Other changes to license information, such as a new business address or name, must also be reported within 90 days (BPC 7083).
From Business and Professions Code 7068.2(a) (with 7083(a))
7. A person with no license is convicted for the first time of acting as a contractor in violation of BPC 7028. What is the maximum criminal penalty?
B. A fine of up to $5,000, up to six months in county jail, or both. Contracting without a license is a misdemeanor, and a first conviction is punishable by a fine of up to $5,000, up to six months in county jail, or both. The 20 percent of the contract price (or $5,000, whichever is greater) fine with at least 90 days in jail is the penalty for a second conviction.
From Business and Professions Code 7028(a) to (c)
California employer payroll taxes and EDD registration, sales and use tax on contractors' materials, the Franchise Tax Board's LLC tax and fee, and reading a balance sheet.
8. A newly licensed sole owner hires her first employee and pays $1,600 in wages on the first payday. Under EDD's 2026 California Employer's Guide, when must she register with EDD for an employer payroll tax account?
D. Within 15 calendar days after paying more than $100 in wages in a calendar quarter. A business becomes a subject employer when it pays more than $100 in wages in any calendar quarter, and it must register with EDD within 15 days. The 20-day deadline belongs to a different form: reporting each new or rehired employee on the DE 34.
From EDD, California Employer's Guide 2026 (DE 44 Rev. 52), When to Register (page 6) and 2026 Forms and Due Dates
9. California has four payroll taxes run by EDD. Which two are withheld from employees' wages rather than paid by the employer?
A. State Disability Insurance (SDI) and Personal Income Tax (PIT). UI and ETT are employer contributions, paid from the employer's own funds. SDI and PIT are withheld from employees' wages, and the employer sends them to EDD.
From EDD, California State Payroll Taxes: Overview
10. A contractor that first became a California employer in 2026 pays the new-employer UI rate. Each of its three employees earns $40,000 in 2026. How much UI tax does it owe on them for the year?
B. $714. UI is charged only on the first $7,000 of each employee's wages in a calendar year, and new employers pay 3.4 percent for two to three years. $7,000 x 3.4% = $238 per employee, and $238 x 3 = $714.
From EDD, California State Payroll Taxes: Overview (Unemployment Insurance) and Contribution Rates, Withholding Schedules, and Meals and Lodging Values (2026)
11. In 2026 a contractor's project manager earns $180,000 in wages. How much State Disability Insurance (SDI) must the contractor withhold from them for the year?
C. $2,340. The 2026 SDI withholding rate is 1.3 percent, and since January 1, 2024 there is no taxable wage limit, so it applies to all wages: $180,000 x 1.3% = $2,340. ($2,160 uses the 2025 rate of 1.2 percent, and $2,520 uses the 2027 rate of 1.4 percent.)
From EDD, Contribution Rates, Withholding Schedules, and Meals and Lodging Values: 2026 SDI Rate
12. Under the California Department of Tax and Fee Administration's Regulation 1521, how is a construction contractor treated for sales and use tax on the lumber, drywall and concrete it furnishes and installs under a lump-sum contract?
D. As the consumer of the materials, so sales or use tax applies to its purchase or use of them. Construction contractors are consumers of the materials they furnish and install, so sales or use tax applies when the materials are sold to or used by the contractor, and the contractor pays it on its cost. Fixtures are treated differently: contractors are retailers of the fixtures they furnish and install.
From CDTFA Regulation 1521(b)(2)(A)1, Materials (with 1521(b)(2)(B)1, Fixtures)
13. A California LLC contractor expects total California income of $620,000 for its 2026 tax year. How much does it owe the Franchise Tax Board for the year in annual tax plus LLC fee?
D. $3,300. Every LLC organized or doing business in California pays the $800 annual tax, and an LLC with total California income of $500,000 to $999,999 also pays a $2,500 LLC fee: $800 + $2,500 = $3,300. The annual tax is due by the 15th day of the 4th month of the tax year and the fee is estimated and paid by the 15th day of the 6th month.
From Franchise Tax Board, Limited liability company: Annual tax and LLC fee
14. A contractor's balance sheet shows cash of $40,000, contract receivables of $95,000, materials inventory of $15,000, trucks and equipment of $120,000, accounts payable of $60,000, payroll taxes owed of $8,000, and an equipment loan of $70,000 with nothing due in the next 12 months. What is its working capital?
B. $82,000. Working capital is current assets minus current liabilities. Current assets are those expected to turn into cash within a year ($40,000 + $95,000 + $15,000 = $150,000); trucks and equipment are fixed assets. Current liabilities are those due within a year ($60,000 + $8,000 = $68,000); the loan is long-term. $150,000 - $68,000 = $82,000.
From SEC, Beginners' Guide to Financial Statements: Balance Sheets and Financial Statement Ratios and Calculations (Working Capital)
Hiring, paying and keeping records for employees in California: minimum wage, overtime, breaks, sick leave, final pay, workers' compensation and who counts as an employee.
15. What is California's statewide minimum wage for 2026 (effective January 1, 2026) for a contractor with 12 employees, where no higher city, county or industry minimum applies?
C. $16.90 per hour. Since January 1, 2026 the state minimum wage is $16.90 an hour for all employers, whatever their size (it was $16.50 in 2025 and $16.00 in 2024). Under Labor Code 1182.12 the Department of Finance adjusts it each January 1 for inflation, and some cities and counties set a higher minimum that the employer must pay instead.
From California Labor Commissioner, Minimum Wage Frequently Asked Questions (minimum wage effective January 1, 2026)
16. A nonexempt carpenter earning $30 an hour works 13 hours on a Tuesday, the first day of the workweek, with no alternative workweek schedule. Under Labor Code 510, what does the employer owe for that day?
B. $480. Labor Code 510 pays time and a half for hours over 8 in a workday and double time for hours over 12: 8 hours x $30 = $240, 4 hours (hours 9 to 12) x $45 = $180, and 1 hour (hour 13) x $60 = $60, for $480. Hours over 40 in the workweek also earn time and a half, and on the seventh day of work in a workweek the first 8 hours are paid at time and a half and any hours after 8 at double time.
From California Labor Code 510(a)
17. A nonunion laborer on a construction site works a 9-hour day. Under Labor Code 512 and IWC Wage Order 16, which breaks must the employer provide?
D. One 30-minute meal period and two paid 10-minute rest periods. A meal period of at least 30 minutes is due for a work period of more than 5 hours, and a second one only when the day runs over 10 hours. Rest time is 10 minutes net for every 4 hours worked or major fraction of 4 hours: 9 hours is two full 4-hour blocks plus 1 hour (not a major fraction), so two paid 10-minute rests. For each workday a required meal or rest period is not provided, the employer owes one extra hour of pay at the regular rate.
From IWC Order No. 16-2001, sections 10 (Meal Periods) and 11 (Rest Periods); Labor Code 512(a)
18. In 2026, an employer that gives the full amount of paid sick leave at the start of each year (instead of letting it accrue) must give an eligible nonunion employee at least how much under Labor Code 246?
A. 40 hours or five days. Labor Code 246(d) defines the full amount of leave as five days or 40 hours a year. An employee who works 30 or more days in a year for the employer is covered, accrues at least 1 hour for every 30 hours worked when the leave is not given up front, and may use accrued sick days from the 90th day of employment; an employer may cap use at 40 hours or five days a year.
From California Labor Code 246(a) to (d)
19. Under Labor Code 226(a), how long must a California employer keep a copy of each itemized wage statement and the record of deductions?
C. At least three years. The copies must be kept on file for at least three years at the place of employment or at a central location in California. Each statement shows gross wages, total hours worked (for nonexempt employees), all deductions, net wages, the pay period dates, the employee's name with only the last four digits of the Social Security number or an employee ID, the employer's legal name and address, and every hourly rate with the hours worked at it. Labor Code 1174(d) likewise requires payroll records of daily hours and wages to be kept not less than three years.
From California Labor Code 226(a)
20. A carpenter with no written contract for a definite period quits on a Monday without giving any notice. Under Labor Code 202, when are his final wages due?
A. No later than 72 hours after he quits. An employee who quits without notice must be paid within 72 hours (by mail if he asks and gives an address); one who gives at least 72 hours' notice is paid at the time of quitting. An employee who is fired must be paid immediately (Labor Code 201), and an employer who willfully pays late owes a waiting time penalty of the daily wage for up to 30 days (Labor Code 203).
From California Labor Code 202(a)
21. Under Business and Professions Code 7125 as in effect in 2026, which licensee must keep a Certificate of Workers' Compensation Insurance (or a DIR Certification of Self-Insurance) on file with CSLB even if it has no employees?
B. A C-39 Roofing contractor. A licensee with no employees may file an exemption certifying it employs no one subject to California workers' compensation law, except holders of the C-8 Concrete, C-20 HVAC, C-22 Asbestos Abatement, C-39 Roofing and D-49 Tree Service (under C-61) classifications, who need coverage whether or not they have employees. Under the version of the section that takes effect January 1, 2028, the no-employee exemption is gone for all licensees except joint ventures with no employees.
From Business and Professions Code 7125(a) and (b) (version repealed effective January 1, 2028), CSLB California Contractors License Law & Reference Book, 2026 edition
22. A licensed general contractor hires an individual tile setter as a subcontractor. Under Labor Code 2781, which facts are part of what the contractor must show for the relationship to be judged under Borello instead of the ABC test?
D. The subcontract is in writing and the tile setter holds a CSLB license covering the work. Labor Code 2775 presumes a worker is an employee unless the hiring entity proves all three ABC conditions (free from control, work outside the usual course of its business, independently established trade). Labor Code 2781 sets that test aside for a construction subcontract only if the contractor shows every listed criterion, including a written subcontract, a CSLB license covering the work, any required local business license, a separate business location, authority to hire and fire, financial responsibility shown by insurance, bonds or warranties, and an independently established business.
From California Labor Code 2781 (with 2775(b)(1))
23. Which Industrial Welfare Commission wage order regulates wages, hours and working conditions for on-site construction occupations in California, and must be posted where employees can read it easily?
C. Order No. 16. IWC Order No. 16-2001 covers certain on-site occupations in the construction, drilling, logging and mining industries, and the order itself states that it must be posted where employees can read it easily. It holds the construction rules on overtime, meal and rest periods and the time records the employer must keep.
From IWC Order No. 16-2001 (title and posting notice)
The insurance disclosures CSLB requires and California's mechanics lien, stop payment notice and lien waiver rules (Civil Code 8000 and following).
24. A drywall subcontractor with no contract with the owner first furnishes work on a private project on April 1. To protect its lien, stop payment notice and payment bond rights for all of its work, its preliminary notice must be given no later than how many days after it first furnished work?
B. 20 days. Civil Code 8204 requires the preliminary notice within 20 days after the claimant first furnishes work; a late notice is still allowed but covers only work done in the 20 days before it was served and after. Under Civil Code 8200 it goes to the owner, the direct contractor and any construction lender; a laborer need not give one, and a claimant with a direct contract with the owner gives it only to the construction lender.
From California Civil Code 8204(a) (with 8200)
25. On a private job the owner records a notice of completion. Under Civil Code 8412 and 8414, what is the latest time to record a claim of mechanics lien for the direct (prime) contractor and for a subcontractor?
A. Direct contractor: 60 days after the notice is recorded; subcontractor: 30 days after. A direct contractor records after completing its direct contract and before the earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion or cessation. Any other claimant records after it stops providing work and before the earlier of 90 days after completion or 30 days after the notice is recorded. With no notice recorded, both have until 90 days after completion.
From California Civil Code 8412 and 8414
26. A subcontractor records a claim of mechanics lien on May 1, and no extension of credit is agreed or recorded. Under Civil Code 8460, by when must it file an action to enforce (foreclose) the lien?
D. Within 90 days after recording. The claimant must commence the action within 90 days after recording the claim of lien, or the lien expires and cannot be enforced. If the claimant and owner agree to extend credit and record notice of it, the action is due within 90 days after the credit expires, but never later than one year after completion of the work of improvement.
From California Civil Code 8460
27. A supplier with lien rights on a private project, who gave a proper preliminary notice, serves a stop payment notice on the owner before the lien recording deadline. If no payment bond has been recorded, what must the owner do under Civil Code 8522?
C. Withhold from the direct contractor enough money to pay the claim. Any person with a lien right other than the direct contractor may give the owner a stop payment notice (Civil Code 8520), and the owner must then withhold from the direct contractor enough of the money due or to become due to pay the claim. An owner who recorded a payment bond may choose not to withhold but must send the claimant a copy of the bond within 30 days. The notice is valid only if the preliminary notice was given and it is served before the lien recording deadline (Civil Code 8508).
From California Civil Code 8522 (with 8520)
28. A subcontractor must sign a lien waiver to receive a progress payment and is handed a check that has not yet cleared the bank. Which statutory form should it sign?
A. Conditional Waiver and Release on Progress Payment (Civil Code 8132). The conditional progress form is for a progress payment not yet received or paid by check, and it waives lien, stop payment notice and payment bond rights only when the bank actually pays the check. The unconditional forms state the claimant has been paid and bind the claimant even if it was not paid, and a waiver not in substantially the statutory form is void (Civil Code 8132 to 8138).
From California Civil Code 8132 (with 8134, 8136 and 8138)
29. A home improvement contractor has no employees and carries no commercial general liability (CGL) insurance. Under Business and Professions Code 7159(e), what must its home improvement contract include?
B. A CGL notice saying it does not carry CGL insurance, and a workers' compensation notice saying it has no employees and is exempt. Every home improvement contract must include (in the contract form, or in an attachment the contract says is attached) a notice headed "Commercial General Liability Insurance (CGL)" stating that the contractor does not carry it, carries it (naming the insurer and its phone number), is self-insured, or is an LLC with the liability insurance or security the law requires, and a notice headed "Workers' Compensation Insurance" stating either that it has no employees and is exempt or that it insures all employees. CSLB regulation 872 (Title 16) also requires a CGL disclosure statement to accompany every bid and every home improvement contract.
From Business and Professions Code 7159(e)(1) and (2), CSLB California Contractors License Law & Reference Book, 2026 edition
California home improvement contract rules: down payments and progress payments, rights to cancel, service and repair contracts, salespersons, change orders, the lien warning, swimming pools, paying subcontractors and the bar on unlicensed contractors suing.
30. A homeowner signs an $8,500 home improvement contract for a bathroom remodel, with no finance charge. Under Business and Professions Code 7159.5, what is the largest down payment the contractor may take?
B. $850. The down payment may not exceed $1,000 or 10 percent of the contract amount, whichever is less. Ten percent of $8,500 is $850, which is less than $1,000, so $850 is the limit. The contract itself must print the notice that the down payment may not exceed $1,000 or 10 percent of the contract price, whichever is less (7159(d)(8)).
From Business and Professions Code 7159.5(a)(3)
31. A contractor on a home improvement job has not furnished a performance and payment bond, a bond equivalent or an approved joint control. Apart from the down payment, how much may the contractor request or accept before the job is finished?
A. No more than the value of the work performed or the material delivered so far. Except for the down payment, the contractor may neither request nor accept payment that exceeds the value of the work performed or material delivered, and the ban also covers advance payments from a lender or financier. A contractor that furnishes a performance and payment bond, a lien and completion bond, or a bond equivalent or joint control approved by the Registrar is exempt and may accept payment before completion.
From Business and Professions Code 7159.5(a)(5) and (a)(8)
32. A general contractor receives a progress payment from the owner that includes $12,000 for a subcontractor's completed work. Unless they agreed otherwise in writing, how soon must the general contractor pay the subcontractor?
C. Within 7 days after receipt. A prime contractor or subcontractor must pay each subcontractor its share no later than 7 days after receiving each progress payment, unless otherwise agreed in writing. A violation is cause for discipline and carries a penalty, payable to the subcontractor, of 2 percent of the amount due per month; in a good faith dispute the contractor may withhold no more than 150 percent of the disputed amount. The rule covers both private and public works.
From Business and Professions Code 7108.5(a), (b) and (e)
33. A contractor negotiates and signs a $15,000 reroofing contract at the home of a 67-year-old homeowner. It is not a disaster repair job. How long a right to cancel must the contract give her?
B. Five business days. Section 7159 requires a Five-Day Right to Cancel notice for a contract with a senior citizen, and Civil Code 1689.5(f) defines a senior citizen as a person 65 or older. Other buyers get three business days, and a contract to repair damage from a sudden or catastrophic event in a declared emergency carries seven business days. The three- or five-day notice is not required when the contract is negotiated at the contractor's place of business; if the buyer cancels, the contractor must return what was paid within 10 days.
From Business and Professions Code 7159(e)(6) and (e)(7)
34. A homeowner calls an electrician to replace a failed breaker. To write the job as a service and repair contract under Business and Professions Code 7159.10, rather than a full home improvement contract, which set of conditions must it meet (among others)?
D. The price is $750 or less, the homeowner initiated the contact, and no payment is due until the work is done. A service and repair contract must be $750 or less, the buyer must have initiated contact to request the work, the contractor may not sell goods or services beyond what is reasonably needed for the problem, and no payment is due or accepted until the work is completed. If any of these is not met, the full home improvement contract rules of 7159 apply, including the right to cancel, regardless of the price.
From Business and Professions Code 7159.10(a) and (b)
35. A licensed remodeling contractor hires a person on commission to go door to door selling window replacement jobs. The person is not an officer, partner or qualifier of the company. What must the person hold before soliciting or negotiating these contracts?
C. A home improvement salesperson registration with the CSLB. A home improvement salesperson must register with the CSLB and, before acting, must tell the owner the business name and license number of the contractor they represent. Selling home improvements without a current registration at the time of the sale is a misdemeanor (7153). Officers of record, general partners on the license, qualifying individuals and people who only set appointments for a registered salesperson are among those exempt.
From Business and Professions Code 7152(b), (c) and (d)
36. On a home improvement job the homeowner asks for an extra window. Under Business and Professions Code 7159.6, the change order for this extra work is enforceable against the buyer only if it sets out which of the following?
D. The scope of the extra work, the amount added or subtracted, and the effect on progress payments or the completion date. A change order must state the scope of the work, the amount added to or subtracted from the contract, and its effect on the progress payments or the completion date, and the buyer may not require extra work without written authorization. Section 7159(d) adds that changes must be in writing and signed by the parties before the work they cover starts. A contractor who skips these steps may still recover for the work through remedies that prevent unjust enrichment.
From Business and Professions Code 7159.6
37. The Mechanics Lien Warning in a home improvement contract tells the owner that a subcontractor or material supplier may send a Preliminary Notice up to how long after starting work or supplying material?
B. 20 days. The required warning explains that unpaid subcontractors, suppliers and laborers may record a mechanics lien even if the owner paid the contractor in full, that the Preliminary Notice can come up to 20 days after the work starts or the material is supplied, and that joint checks are one way to protect against liens. A contractor who furnishes an approved performance and payment bond, lien and completion bond, bond equivalent or joint control does not have to include the warning (7159.5(a)(8)).
From Business and Professions Code 7159(e)(4)
38. A person who has never held a California contractor license finishes a $30,000 kitchen remodel, and the homeowner refuses to pay the last $12,000. Under Business and Professions Code 7031, which is true?
A. The person cannot sue to collect, and the homeowner may sue to recover all compensation already paid. No one acting as a contractor may sue in a California court to collect pay for work that requires a license without alleging they were duly licensed at all times during the work, regardless of the merits of the claim. The person who used an unlicensed contractor may sue to recover all compensation paid, and a security interest taken for the payment is unenforceable. A court may not apply substantial compliance to someone who has never been licensed in California.
From Business and Professions Code 7031(a), (b), (c) and (e)
39. A pool builder's contract for an in-ground swimming pool leaves out the plan and scale drawing and the schedule of progress payments. Under Business and Professions Code 7167, what is the effect?
D. The contract is void and unenforceable by the contractor as contrary to public policy. A contract whose primary purpose is building a swimming pool is void and unenforceable by the contractor if it does not substantially comply with 7159's rules on the lien release statement, the change-order form, the project description, the down payment and the progress payment schedule. For a pool, the project description must include a plan and scale drawing showing the shape, size, dimensions and the construction and equipment specifications (7159(d)(7)).
From Business and Professions Code 7167(a)
DIR contractor registration, prevailing wages and certified payroll, and apprentice ratios on California public works.
40. Under Labor Code 1725.5, a contractor or subcontractor must be registered with the Department of Industrial Relations to bid on, be listed in a bid for, or work on a public works contract. Registration is not required on a construction, alteration, demolition, installation or repair project of how much or less?
C. $25,000. Registration does not apply to construction, alteration, demolition, installation or repair projects of $25,000 or less, or to maintenance projects of $15,000 or less. A registered contractor pays an annual renewal fee on or before July 1 and must show workers' compensation coverage, a contractor license where required, no delinquent wage liability and no current debarment. Keep it apart from the $1,000 prevailing wage threshold (Labor Code 1771) and the $30,000 apprenticeship threshold (Labor Code 1777.5(o)).
From Labor Code 1725.5(a) and (f) (version operative July 1, 2026)
41. Under Labor Code 1771, prevailing wages must be paid to all workers employed on public works, except on public works projects of how much or less?
A. $1,000. Prevailing wages, including the holiday and overtime rates, must be paid on public works projects over $1,000 done under contract (not work a public agency does with its own forces). An awarding body with a labor compliance program approved by the Director of Industrial Relations may choose not to require them on construction projects of $25,000 or less, or alteration, demolition, repair or maintenance projects of $15,000 or less (Labor Code 1771.5). Each contractor and subcontractor must keep payroll records showing every worker's hours and actual wages, verified under penalty of perjury, and must file a certified copy within 10 days of a written request or forfeit $100 per calendar day for each worker (Labor Code 1776).
From Labor Code 1771
42. On a public works contract of $30,000 or more, journeymen in an apprenticeable trade will work 2,400 hours, none of them over 8 hours a day or 40 hours a week. Unless an exemption applies, what is the minimum number of apprentice hours the contractor must employ under Labor Code 1777.5?
C. 480 hours. The ratio may never be less than one hour of apprentice work for every five hours of journeyman work, so 2,400 divided by 5 gives 480 hours. Journeyman hours over 8 a day or 40 a week do not count toward the ratio, and the rule does not apply to general contracts, or specialty contracts not bid through a general or prime contractor, of less than $30,000.
From Labor Code 1777.5(g), (h) and (o)
Cal/OSHA rules for contractors: the Injury and Illness Prevention Program, toolbox meetings, reporting serious injuries, trench permits and heat illness prevention.
43. Under Title 8, section 3203, a California employer's written Injury and Illness Prevention Program must, at a minimum, do which of the following?
D. Identify the person or persons with authority and responsibility for carrying it out. The written program must identify who is responsible for it and include a system for employee compliance, a system for communicating with employees, procedures to find hazards through scheduled periodic inspections, a procedure to investigate injuries and illnesses, timely correction of hazards, and training. Construction employers must have one under Title 8, section 1509(a), and records of inspections and of training are kept for at least one year.
From Title 8, California Code of Regulations, section 3203(a) and (b)
44. Under Title 8, section 1509 of the Construction Safety Orders, how often must supervisors hold toolbox or tailgate safety meetings with their crews?
C. At least every 10 working days. Supervisory employees must hold toolbox or tailgate safety meetings, or the equivalent, with their crews at least every 10 working days. The same section requires every construction employer to have an Injury and Illness Prevention Program and a written Code of Safe Practices for its operations, posted at each job site office or given to each supervisor to keep readily available.
From Title 8, California Code of Regulations, section 1509(a) to (e)
45. One of your employees suffers a serious injury on a job site. Under Title 8, section 342, how soon must you report it to Cal/OSHA, absent exigent circumstances?
A. As soon as practically possible, and no later than 8 hours after you knew or should have known. A serious injury or illness, or a death, connected with employment must be reported immediately, meaning as soon as practically possible and no later than 8 hours after the employer knows, or with diligent inquiry would have known, of it. Only if the employer can show exigent circumstances may the report be made up to 24 hours after the incident. The report is made to the Division of Occupational Safety and Health by telephone or its online mechanism.
From Title 8, California Code of Regulations, section 342(a)
46. A contractor will dig a trench that workers must enter. Under Labor Code 6500, at what depth does the contractor need a Cal/OSHA permit before the work starts?
B. 5 feet or deeper. Cal/OSHA requires a permit before constructing trenches or excavations 5 feet or deeper into which a person is required to descend. Under Title 8, section 341(d)(5) and (e), the employer may hold an annual or a project permit, and excavations for swimming pools, emergency repair of underground facilities and trenches no one has to enter are among the exceptions.
From Labor Code 6500(a)(1)
47. On an outdoor construction site where drinking water is not plumbed or continuously supplied, how much water must the employer provide at the start of the shift under Title 8, section 3395, unless it has effective procedures to replenish it?
D. One quart per employee per hour for the entire shift. The water must be fresh, pure, suitably cool, free of charge and as close as practicable to where employees work, and there must be enough at the start of the shift for one quart per employee per hour for the entire shift. An employer may start with less only if it has effective procedures to replenish the water during the shift so each employee can drink one quart or more per hour.
From Title 8, California Code of Regulations, section 3395(c)
48. Under Cal/OSHA's heat illness standard (Title 8, section 3395), above what outdoor temperature must an employer have shade present at all times while employees are working outdoors?
B. 80 degrees Fahrenheit. Shade must be present when the temperature exceeds 80 degrees Fahrenheit, enough for everyone on a rest or recovery period to sit fully in the shade; at 80 degrees or below the employer must still give timely access to shade on request. In construction, high-heat procedures (such as effective observation and communication) start when the temperature equals or exceeds 95 degrees Fahrenheit.
From Title 8, California Code of Regulations, section 3395(a), (d) and (e)
Beyond the license in California, a new contracting business needs a way to schedule and bill jobs, insurance and, where the state asks for one, a bond.
Offered to tradespeople starting their own business. We may earn a share of what you pay if you buy through these links. It never changes your price, and the sellers have no say in what we publish about licensing.
More free practice tests: EPA 608 Practice Test · Journeyman Electrician Practice Test · Journeyman Plumber Practice Test · OSHA 10 Practice Test · OSHA 30 Practice Test · Electrical Aptitude Test Practice · UA Plumbers and Pipefitters Aptitude Test Practice · EEI CAST Test Practice · Contractor Business and Law Practice Test · Florida Business and Finance Exam Practice Test · Arizona Statutes and Rules Exam Practice Test · Nevada Business and Law Exam Practice Test · Utah Business and Law Exam Practice Test · Louisiana Business and Law Exam Practice Test · South Carolina Business and Law Exam Practice Test · North Carolina General Contractor Exam Practice Test · Oregon CCB Test Practice Test · New Mexico Business and Law Exam Practice Test · Alabama Business and Law Exam Practice Test · Hawaii Business and Law Exam Practice Test · OSHA 10 General Industry Practice Test · Forklift Practice Test
No. The bodies that give the real exam keep its questions to themselves. Each question here is written for the rules or skills the exam tests, and its explanation shows the working or names the section of the regulation or code it comes from, so you learn the rule rather than one answer.
Yes. All 48 questions and their explanations are free, with no sign-up. Your answers stay in your browser.
Checked against the rules in force on 2026-11-26. Rules and exam formats change: check the current rule and your exam provider's own information before the exam.