Skip to content

Free practice test

New Mexico Business and Law Exam Practice Test

Practice for the Business and Law exam New Mexico asks of contractor license applicants, on what is New Mexico's own: the Construction Industries Licensing Act and its rules, the qualifying party and bonds, mechanics' liens, prompt payment, workers' comp and gross receipts tax. Pick an answer to see whether it is right and the statute behind it.

39
practice questions
each with its answer explained
5
sections
Licensing and the qualifying party, Bond, renewal and discipline, Mechanic's liens, Prompt payment, Workers' comp, employees and taxes
75%
to pass the real exam
as its official rules state

What the real exam is like

Passing it, with the trade exam for your classification, is what New Mexico's Construction Industries Division asks of the qualifying party before it issues a license.

  • A person who wants to become a qualifying party for a New Mexico contractor license must pass the exam for the classification sought plus a Contractor's Business and Law exam, or take an approved Business and Law course instead. (CID: How to Apply for a Construction Industries License, step 2)
  • The PSI Business and Law exam has 50 questions, 130 minutes, and requires 75 percent (38 points) to pass; the exam fee is $68.88. (PSI Contractor Examinations Candidate Information Bulletin (updated 4/3/2026), Business and Law Examination)
  • The exam is open book. Bound references allowed in the exam center include the NASCLA Contractors Guide to Business, Law and Project Management (Basic, 14th Edition), the Construction Industries Licensing Act (NMSA chapter 60, article 13) and New Mexico's contractor license requirement rule (14.6.3 NMAC); any reference with writing in it is not allowed, and candidates may use a silent, non-printing, non-programmable calculator. (PSI Contractor Examinations Candidate Information Bulletin (updated 4/3/2026), Reference List)
  • Applicants must be pre-approved before they can schedule: send the QP application and a notarized work experience affidavit with a $36 fee to PSI in Albuquerque, then register and schedule with PSI online, by phone, fax or mail. (CID: How to Apply for a Construction Industries License, steps 3 and 4)
  • The content outline covers Licensing Requirements (8 items), Business Organization and Financial Management (8), Contracts (8), Estimating and Bidding (5), Tax Laws (5), Project Management and Lien Law (5), Labor Laws (4), Risk Management (4) and Environmental and Safety (3). You must pass the Business and Law exam and the trade exam within one year of each other. (PSI Contractor Examinations Candidate Information Bulletin (updated 4/3/2026), Content Outline)

The practice test

Pick an answer to see whether it is right. Each explanation shows why, with the rule or the working behind it, so a wrong answer still teaches you something.

0 of 39 answered

Licensing and the qualifying party (8) · Bond, renewal and discipline (8) · Mechanic's liens (8) · Prompt payment (7) · Workers' comp, employees and taxes (8)

Licensing and the qualifying party

Who needs a New Mexico contractor license, the qualifying party, experience and the exam rule.

  1. 1. Under the New Mexico Construction Industries Licensing Act, when may a contractor submit a bid on a contract?

    Show the answer

    A. Only if the contractor holds a valid CID license to bid and perform that type of work. No bid may be submitted unless the contractor already has a valid license from the division covering the work. The one carve-out is a contractor bidding a New Mexico highway project with federal funds, who may bid first and must apply for a license on becoming the apparent successful bidder.

    From NMSA 60-13-12(B) and (C) (Construction Industries Licensing Act)

  2. 2. In New Mexico, a contractor license is issued to which of the following?

    Show the answer

    D. A qualified business entity that employs or is owned by a certified qualifying party. CID licenses go to business entities that employ or are owned by at least one qualifying party certified for the classification. The qualifying party's certificate is personal and not transferable, and the license is not transferable either.

    From 14.6.3.8 NMAC A(3)(a)

  3. 3. How much practical or related trade experience must an applicant show, and within what window, before a New Mexico contractor license is issued (without a rule reducing it)?

    Show the answer

    B. Four years within the 10 years immediately before application. The Act requires four years of practical or related trade experience in the type of construction, within the 10 years before application. The commission may reduce it for a particular craft, but never below two years, and CID's rule says the experience must be shown before the applicant may sit the qualifying exam.

    From NMSA 60-13-14(B)(8) (Construction Industries Licensing Act)

  4. 4. A New Mexico qualifying party applicant must satisfy the business and law knowledge requirement. Which of these also satisfies it?

    Show the answer

    A. A certificate of completion of a business and law course from an institute approved by the commission. In place of the business and law examination, an applicant may present a certificate from a business and law course of study offered by an accredited education institute approved by the commission. The course and its materials must be available in English and Spanish.

    From NMSA 60-13-16(C) (Construction Industries Licensing Act)

  5. 5. What is the minimum age for an individual to be issued a New Mexico qualifying party certificate?

    Show the answer

    C. 18 years. Qualifying party certificates are issued only to individuals 18 or older. A related rule bars licensing a business entity whose majority owner is 17 or younger.

    From 14.6.3.8 NMAC E(1)(a)

  6. 6. A qualifying party leaves the company. How soon must the licensee and the qualifying party each notify CID of the separation?

    Show the answer

    A. Within 30 days. Both the licensee and the qualifying party must notify the division within 30 days. The license is then suspended 120 days from the termination date and canceled unless another properly certified qualifying party is approved.

    From NMSA 60-13-25 (Construction Industries Licensing Act)

  7. 7. What is the passing score on a New Mexico CID qualifying exam under 14.6.3 NMAC?

    Show the answer

    B. 75 percent or higher. The rule sets a passing exam score at seventy-five percent or higher. A candidate who fails or misses an exam may retake it after reapplying and paying the fee, but may not take the exam more than twice in any 30-day period.

    From 14.6.3.8 NMAC G(2)(c) and (d)

  8. 8. Two New Mexico contractors want to submit one joint bid and work together as partners on the job. What does the rule require?

    Show the answer

    C. The two must operate as a validly licensed joint venture, and each entity in it must hold a valid New Mexico contractor license. No two or more persons may submit a joint bid or jointly engage in contracting unless they operate as a validly licensed joint venture. Each entity comprising the joint venture must hold a valid New Mexico contractor license and be authorized to do business in the state.

    From 14.6.3.8 NMAC B(2)

Bond, renewal and discipline

The $10,000 bond, license term and renewal, suspension, revocation and penalties.

  1. 9. What is the amount of the bond a New Mexico contractor must furnish as proof of responsibility?

    Show the answer

    C. $10,000. The proof of responsibility is a $10,000 bond acceptable to the director and underwritten by a corporate surety authorized to do business in New Mexico. It is required for a new license and for each renewal.

    From NMSA 60-13-49(B) (Construction Industries Licensing Act)

  2. 10. Claims against a New Mexico license bond must be made within what period?

    Show the answer

    D. Two years after final inspection by the code jurisdiction or two years after the certificate of occupancy, whichever is earlier. Payment from the bond may only cure code violations caused by the licensee, certified by the division and left uncorrected. Claims must come within two years of final inspection or of the certificate of occupancy, whichever is earlier, and the surety's total liability is capped at the bond's face amount.

    From NMSA 60-13-49(B)(1) and (2) (Construction Industries Licensing Act)

  3. 11. A contractor's bond is canceled mid-license. If the contractor has not given CID proof of a new bond by what point is the license subject to revocation?

    Show the answer

    B. The 40th day after cancellation. The division notifies the licensee that a new bond is required. If proof of a new bond is not provided before the 40th day after cancellation, expiration or ineffectiveness, the license is subject to revocation for failure of proof of responsibility.

    From NMSA 60-13-49(B)(5) (Construction Industries Licensing Act)

  4. 12. Under the Act, how long is a New Mexico contractor's license normally issued for, and how does it end if not renewed?

    Show the answer

    C. Two years from issuance (or as the division sets, never under one year), and it is suspended by operation of law if renewal is not filed by the last working day before expiration. Contractor licenses expire two years after issuance or as the division determines, but never in less than one year, with a staggered system allowed. Failing to renew by the last working day before expiration suspends the license by operation of law.

    From NMSA 60-13-18(B) and (F) (Construction Industries Licensing Act)

  5. 13. A New Mexico contractor's license expired and is suspended. Which statement about renewing it is correct?

    Show the answer

    D. If not renewed within a three-month period it is canceled, and a late renewal costs $1 a day for up to 30 days, then twice the renewal fee. A suspended license is canceled unless renewed within three months. The renewal fee for a suspended license adds $1.00 for each day elapsed up to 30 days, and after that twice the renewal fee.

    From NMSA 60-13-18(G) (Construction Industries Licensing Act)

  6. 14. How long may the New Mexico Construction Industries Commission suspend a license for a single definite suspension?

    Show the answer

    D. Not more than 90 consecutive days. Suspensions are for a definite period not exceeding ninety consecutive days, and a suspension does not prevent later revocation for cause. At the end of the period the commission reviews the license to decide whether to reinstate or revoke it.

    From NMSA 60-13-28(A) and (C) (Construction Industries Licensing Act)

  7. 15. A contractor has done an $80,000 job and the commission assesses the maximum administrative penalty for a violation, with no prior suspension, revocation or penalty. What is the most it can assess?

    Show the answer

    C. $8,000. When the contract or work exceeds $5,000, the penalty is up to ten percent of its dollar amount but not less than $500. Ten percent of $80,000 is $8,000. For work of $5,000 or less the penalty is $300 to $500, and it doubles for a repeat offender.

    From NMSA 60-13-23.1(A) and (B) (Construction Industries Licensing Act)

  8. 16. Which of these is a listed ground for revoking or suspending a New Mexico contractor license?

    Show the answer

    A. Acting as a licensee under a name other than the one on the license. Section 60-13-23 lists causes including knowingly contracting beyond the license scope, failing to maintain workers' compensation insurance or the bond, allowing an unlicensed person to use the license, and acting under any other name than the one on the license.

    From NMSA 60-13-23(K) (Construction Industries Licensing Act)

Mechanic's liens

Filing, notice, enforcement and cancelation under NMSA chapter 48, article 2, what an unlicensed contractor loses, and the penalty for unlicensed work.

  1. 17. Under the New Mexico mechanic's lien statute, within how many days after completing the contract must an original contractor file its claim of lien with the county clerk?

    Show the answer

    D. 120 days. An original contractor files within 120 days after completion of its contract. Every other claimant (subcontractors, suppliers and the like) must file within 90 days after completion of the building, improvement or structure or of the alteration or repair.

    From NMSA 48-2-6(A) (mechanic's and materialman's liens)

  2. 18. After filing a claim of lien, the claimant must send a copy to the owner or reputed owner within how many days?

    Show the answer

    B. Within 15 days. The claimant must mail, email, send by certified mail or hand deliver a copy of the filed claim to the owner within fifteen days of filing. Failing to serve it may bar recovery of interest, attorney fees or costs.

    From NMSA 48-2-6(B) (mechanic's and materialman's liens)

  3. 19. A mechanic's lien claim in New Mexico is filed. How long does the lien stay valid if no suit or binding arbitration is started to enforce it?

    Show the answer

    C. Two years after the claim of lien is filed. No lien remains valid longer than two years after the claim was filed unless court proceedings or binding arbitration to enforce it have begun within that time.

    From NMSA 48-2-10 (mechanic's and materialman's liens)

  4. 20. A New Mexico lien claimant is a subcontractor on a commercial job, claiming more than $5,000. To enforce the lien it must give written notice of its right to claim a lien to the owner or the original contractor within how many days of first furnishing work or materials?

    Show the answer

    C. 60 days. A lien over $5,000 cannot be enforced unless the claimant gave written notice of its right to claim a lien within sixty days after first furnishing work or materials, by certified mail with return receipt, fax with acknowledgment or personal delivery. The requirement does not apply to residential property of four or fewer units, to original contractors, or to those who contract directly with the original contractor.

    From NMSA 48-2-2.1(A) and (B) (mechanic's and materialman's liens)

  5. 21. A contractor performs work in New Mexico that required a license but does not hold one. What is its position on a mechanic's lien and on suing for payment?

    Show the answer

    D. It has no right to file a mechanic's lien, and must allege and prove it was licensed to sue for compensation. An unlicensed contractor has no right to file or claim any mechanic's lien, and cannot bring any court action to collect compensation without alleging and proving it was a duly licensed contractor when the cause of action arose.

    From NMSA 60-13-30 (Construction Industries Licensing Act)

  6. 22. An owner learns that a contractor is about to build on the owner's land. How can the owner avoid having the land subject to a lien for that work?

    Show the answer

    B. Post a written notice of non-responsibility in a conspicuous place on the land within three days of learning of the work. Improvements built with the owner's knowledge are deemed built at the owner's instance unless the owner, within three days of learning of the construction, posts a written notice in a conspicuous place that the owner will not be responsible.

    From NMSA 48-2-11 (mechanic's and materialman's liens)

  7. 23. An owner or original contractor wants a recorded New Mexico lien canceled while the dispute continues. What procedure does the statute give?

    Show the answer

    A. Petition the district court, which sets an amount of security; once deposited, the court cancels the lien and the claim attaches to the security. The owner or original contractor petitions the district court. The judge sets security sufficient for the recorded demands plus damages, costs and fees; once it is deposited the court immediately cancels the lien, which then attaches to the security. One security cannot cover more than one claimant.

    From NMSA 48-2-9(A) to (C) (mechanic's and materialman's liens)

  8. 24. Which of the following is NOT a penalty for acting as a contractor without a license on a $20,000 job in New Mexico?

    Show the answer

    B. A felony conviction. Acting as an unlicensed contractor is a misdemeanor. Where the work exceeds $5,000 the court sentences up to six months in county jail or a fine of ten percent of the work's dollar value, or both. Ten percent of $20,000 is $2,000.

    From NMSA 60-13-52(A)(2) (Construction Industries Licensing Act)

Prompt payment

The Prompt Payment Act: when owners and contractors must pay, interest and final payment.

  1. 25. Under the New Mexico Prompt Payment Act, within how many days after receiving an undisputed request for payment must an owner pay the contractor?

    Show the answer

    B. 21 days. Construction contracts must provide that payment is due within twenty-one days after the owner receives an undisputed request for payment. A local public body may use up to 45 days when grant money funds the project and the contract and plans say so conspicuously.

    From NMSA 57-28-5(A) and (B) (Prompt Payment Act)

  2. 26. An owner receives an undisputed $40,000 pay request and pays it one month late (after the 21 days). Beginning the day after payment was due, what interest does the Act add for that one month?

    Show the answer

    A. $600. Interest is one and one-half percent of the undisputed amount per month or fraction of a month. 1.5% of $40,000 is $600.

    From NMSA 57-28-5(A) (Prompt Payment Act)

  3. 27. A prime contractor is paid by the owner on a New Mexico commercial project. Within how many days must it pay its subcontractors and suppliers their share?

    Show the answer

    D. Within 7 days after receipt of payment. Contractors and subcontractors must pay their subcontractors and suppliers within seven days after receiving payment. Interest of 1.5% a month starts on the eighth day, and the rule applies to all tiers.

    From NMSA 57-28-5(C) (Prompt Payment Act)

  4. 28. An owner receives an improperly completed invoice. What must the owner do under the Prompt Payment Act?

    Show the answer

    D. Notify the sender within seven days of receipt how it is improperly completed, after which no duty to pay arises until it is resubmitted complete. The owner must tell the sender within seven days how the invoice is improperly completed, and has no further duty to pay on it until it is resubmitted complete.

    From NMSA 57-28-5(A) (Prompt Payment Act)

  5. 29. The Prompt Payment Act in New Mexico does not apply to which kind of construction contract?

    Show the answer

    C. Contracts for residential property with four or fewer dwelling units. The Act does not apply to construction contracts for residential property containing four or fewer dwelling units.

    From NMSA 57-28-3 (Prompt Payment Act)

  6. 30. Under the Prompt Payment Act, ten days after certification of completion, what must be paid to a contractor?

    Show the answer

    A. Any amounts remaining due, on presentation of a release and certified voucher, any required release of claims and liens, and proof of completion. Ten days after certification of completion, any remaining amounts due under the contract are paid on presentation of a properly executed release and certified voucher, a release of claims and liens (other than stated exceptions) if required, and proof of completion.

    From NMSA 57-28-8 (Prompt Payment Act)

  7. 31. In an action to enforce the Prompt Payment Act, what may the New Mexico court award?

    Show the answer

    D. Court costs and reasonable attorney fees. The court may award court costs and reasonable attorney fees in an action to enforce the Act.

    From NMSA 57-28-11 (Prompt Payment Act)

Workers' comp, employees and taxes

Workers' compensation, who is an employee, and New Mexico gross receipts tax.

  1. 32. How many employees must a New Mexico employer have before the Workers' Compensation Act applies, and how does that change for licensed contractors?

    Show the answer

    C. Three or more workers; for employers doing work that requires a Construction Industries Licensing Act license, it applies regardless of the number of employees. The Act applies to employers of three or more workers and to all employers engaged in activities required to be licensed under the Construction Industries Licensing Act, regardless of how many employees they have.

    From NMSA 52-1-6(A) (Workers' Compensation Act)

  2. 33. A New Mexico licensed contractor lets its workers' compensation insurance lapse. What does the Act say about that?

    Show the answer

    A. It is a ground for revocation or suspension of the license. Failure to maintain workers' compensation insurance as the Workers' Compensation Act requires is listed as a cause for the commission to revoke or suspend a license. CID's application page also notes that coverage is required for all licensed entities.

    From NMSA 60-13-23(I) (Construction Industries Licensing Act)

  3. 34. Under New Mexico's rule for construction, a contractor that is an employer treats a person who provides labor or services as what, unless the standards for an independent contractor are met?

    Show the answer

    B. An employee of the contractor. The statute presumes the person is an employee and not an independent contractor unless the listed standards are met, such as freedom from direction over means and manner of work, supplying own tools, authority to hire and fire, payment on completion of project portions, and representing an independently established business.

    From NMSA 60-13-3.1(A) (Construction Industries Licensing Act)

  4. 35. To count as an independently established business under New Mexico's construction independent-contractor test, how many of the six listed circumstances must exist?

    Show the answer

    D. Four or more. A person is engaged in an independently established business when four or more of the six circumstances exist, such as working from a separate location, buying advertising or business cards, a separate phone listing, working only under written contracts, working for two or more persons in a year, or carrying insurance, bonds or warranties for errors.

    From NMSA 60-13-3.1(A)(6) (Construction Industries Licensing Act)

  5. 36. A contractor intentionally and willfully reports to a state agency that an employee is an independent contractor when the employee does not meet the standards. What is the penalty under the Act?

    Show the answer

    A. A misdemeanor with a fine of up to $5,000, up to six months in jail, or both, and the conviction is grounds for suspending, revoking or refusing to renew the license. Such a report is a misdemeanor punishable by a fine of not more than $5,000, imprisonment up to six months, or both. A conviction is also grounds for the commission to suspend, revoke or refuse to renew the contractor's license.

    From NMSA 60-13-3.1(C) and (D) (Construction Industries Licensing Act)

  6. 37. What does the New Mexico gross receipts tax apply to?

    Show the answer

    A. The gross receipts of a person engaging in business in New Mexico, as an excise tax for the privilege of doing business. The gross receipts tax is an excise tax on the privilege of engaging in business, equal to a percentage of gross receipts. The statute sets the state rate by date, and it covers receipts from performing services in New Mexico, not only from selling goods.

    From NMSA 7-9-4 (Gross Receipts and Compensating Tax Act)

  7. 38. For gross receipts tax purposes in New Mexico, how are construction activities treated?

    Show the answer

    D. As a service, which includes construction activities and the materials that become part of the project. The Act's definition of service includes construction activities and all tangible personal property that will become an ingredient or component part of a construction project. Sales of such materials to persons in the construction business are sales of tangible personal property.

    From NMSA 7-9-3(S) (Gross Receipts and Compensating Tax Act)

  8. 39. What proof of tax status must a New Mexico contractor license applicant submit?

    Show the answer

    D. Proof of registration with the taxation and revenue department and a current identification tax number. An applicant must submit proof of registration with the taxation and revenue department and a current identification tax number. CID's application page lists a Tax and Revenue Department registration certificate with the license application.

    From NMSA 60-13-14(B)(6) (Construction Industries Licensing Act)

0 of 39 answered

Setting up your own shop

Beyond the license in New Mexico, a new contracting business needs a way to schedule and bill jobs, insurance and, where the state asks for one, a bond.

Offered to tradespeople starting their own business. We may earn a share of what you pay if you buy through these links. It never changes your price, and the sellers have no say in what we publish about licensing.

Questions

Are these the real New Mexico Business and Law Exam exam questions?

No. The bodies that give the real exam keep its questions to themselves. Each question here is written for the rules or skills the exam tests, and its explanation shows the working or names the section of the regulation or code it comes from, so you learn the rule rather than one answer.

Is the practice test free?

Yes. All 39 questions and their explanations are free, with no sign-up. Your answers stay in your browser.

Checked against the rules in force on 2026-11-26. Rules and exam formats change: check the current rule and your exam provider's own information before the exam.