Practice for the Business and Law exam Hawaii asks of contractor license applicants, on what is Hawaii's own: license classes, bonds and insurance, the residential contract and disclosure rules, the recovery fund, mechanics' liens, workers' comp and the general excise tax. Pick an answer to see whether it is right and the statute behind it.

32
practice questions
each with its answer explained
5
sections
Who needs a license, Classes, insurance, bond and RME, Homeowner contracts and payment, Recovery fund, penalties and records, Liens, workers' comp and tax
75%
to pass the real exam
as its official rules state

What the real exam is like

Passing it, with the trade exam for your classification, is what the Hawaii Contractors License Board asks of the responsible managing employee before it issues a license.

  • Every new applicant approved to take the contractor examinations must take the Business and Law examination; a licensee approved for an additional classification takes only the exam for that classification. (PSI Hawaii Contractor Examinations Candidate Information Bulletin (1/20/2026))
  • The Business and Law exam has 80 questions, a 180 minute time limit and a 75 percent minimum passing score. Up to ten unscored experimental questions may also be given, and their time does not count. (PSI Hawaii Contractor Examinations Candidate Information Bulletin (1/20/2026))
  • The exam is closed book. The NASCLA Contractors Guide to Business, Law and Project Management, Hawaii edition, is not allowed in the examination center. It tests payroll taxes, workers' compensation, unemployment compensation, lien laws and other laws that affect a contractor's daily operations. (PSI Hawaii Contractor Examinations Candidate Information Bulletin (1/20/2026))
  • Since January 2023 PSI Services runs the exams. You may register only after the Board approves your application and sends an approval letter, and you must pass within six months or file a new application. (DCCA Contractors License Board, Examination)
  • Hawaii sets the passing grade at 75 percent for each part of any contractor examination, and an applicant who fails may schedule another exam and pay the fees again. (HAR 16-77-44 Passing grade and 16-77-45 Failure to pass examination)

The practice test

Pick an answer to see whether it is right. Each explanation shows why, with the rule or the working behind it, so a wrong answer still teaches you something.

0 of 32 answered

Who needs a license (6) · Classes, insurance, bond and RME (6) · Homeowner contracts and payment (6) · Recovery fund, penalties and records (7) · Liens, workers' comp and tax (7)

Who needs a license

Who counts as a contractor, the small-job and owner-builder exemptions, and what an unlicensed contractor gives up under HRS chapter 444.

  1. 1. Under HRS 444-2, a project is outside the licensing law if the aggregate contract price for labor and materials is not more than what amount (and no building permit is required)?

    Show the answer

    C. $1,500. HRS 444-2(4) exempts any project or operation whose aggregate contract price for labor and materials is not more than $1,500. It does not apply where a building permit is required.

    From HRS 444-2 Exemptions

  2. 2. A homeowner hires an unlicensed worker for a $900 job that needs a county building permit. Under HRS 444-2(4), is the job exempt from licensing?

    Show the answer

    A. No, the small-job exemption does not apply where a building permit is required, whatever the price. The $1,500 exemption in HRS 444-2(4) does not apply in any case where a building permit is required, regardless of the aggregate contract price. It also fails where the job is part of a larger project or is split into small contracts to evade the chapter.

    From HRS 444-2 Exemptions

  3. 3. Under HRS 444-2.5, the sale or lease of an owner-built structure within what period after completion is prima facie evidence that it was built for sale or lease?

    Show the answer

    D. One year. HRS 444-2.5(b) says proof of sale or lease, or offering for sale or lease, within one year after completion is prima facie evidence that the work was done for sale or lease, which defeats the owner-builder exemption (with exceptions such as permits valued under $10,000).

    From HRS 444-2.5 Owner-builder exemption

  4. 4. An owner-builder exempt under HRS 444-2.5 uses an unlicensed person to work on the project. How must the owner treat that person?

    Show the answer

    B. As the owner's employee: deduct FICA and withholding taxes and provide workers' compensation. HRS 444-2.5(a)(3)(D) requires the owner to deduct FICA and withholding taxes and provide workers' compensation for people on the job who are not licensed under chapter 444 or 448E, who are considered the owner's employees.

    From HRS 444-2.5 Owner-builder exemption

  5. 5. After an owner-builder's project is complete, the owner must keep the permit and contract records for three years and make them available for inspection within how many business days of a department request?

    Show the answer

    C. Seven. HRS 444-2.5(a)(5) requires the records to be kept three years from completion and made available within seven business days upon request by the department.

    From HRS 444-2.5 Owner-builder exemption

  6. 6. A contractor who was not licensed when the contract was made sues the owner for payment for work done. Under HRS 444-22, what is the result?

    Show the answer

    A. The contractor cannot recover for the work or materials, or their reasonable value, in a civil action. HRS 444-22 bars a person who failed to obtain a license before contracting from recovering for work done or materials furnished, either on the contract or on the basis of reasonable value. Hawaii courts have applied it even where the other party knew the contractor was unlicensed.

    From HRS 444-22 Civil action

Classes, insurance, bond and RME

The A, B and C classifications, keeping a license in force, the surety bond and the responsible managing employee.

  1. 7. Under HRS 444-7(c), a general building contractor's principal business is a structure whose construction requires the use of how many unrelated building trades or crafts?

    Show the answer

    D. More than two. HRS 444-7(c) defines the general building contractor by structures that require more than two unrelated building trades or crafts. The general engineering contractor (A) works on fixed works such as highways and dams, and the specialty contractor (C) on a specialized trade.

    From HRS 444-7 Classification

  2. 8. Under HRS 444-8(c), a specialty contractor may take a contract that also involves other trades only if the work in those other trades is what?

    Show the answer

    B. Incidental and supplemental to the work in the trade the contractor is licensed for. HRS 444-8(c) allows a specialty contractor to take and execute a contract involving two or more crafts if the work outside the licensed craft is incidental and supplemental to the work in the licensed craft.

    From HRS 444-8(c) Powers to classify and limit operations

  3. 9. A licensed contractor's liability insurance is cancelled and not replaced. Under HRS 444-11.1(b), what happens to the license?

    Show the answer

    C. It is automatically forfeited as of the date the insurance is cancelled. HRS 444-11.1(b) says failure to maintain workers' compensation insurance, liability insurance or a required bond causes automatic forfeiture effective on the date of expiration or cancellation. The licensee may then ask for an administrative hearing within sixty days of notice.

    From HRS 444-11.1 Requirements to maintain license

  4. 10. Under HRS 444-11.1(d), a forfeited license that is not restored within how many days after forfeiture requires the person to apply as a new applicant?

    Show the answer

    A. Sixty days. HRS 444-11.1(d) says failure to restore within sixty days after the date of forfeiture results in forfeiture of all fees and requires a new application.

    From HRS 444-11.1 Requirements to maintain license

  5. 11. Under HRS 444-16.5, what is the least amount of surety bond the board may require of a specialty or general contractor?

    Show the answer

    D. $5,000. HRS 444-16.5 lets the board require a bond of not less than $5,000 from a specialty or a general contractor, taking into account the licensee's financial condition and experience. The bond covers wages owed and honest conduct of the business.

    From HRS 444-16.5 Bond

  6. 12. Which of these is required of the principal RME of a contracting entity under HAR 16-77-71?

    Show the answer

    B. Being in residence in Hawaii while the license is in effect or a project is under construction. HAR 16-77-71(a) requires the principal RME to be in a position to secure full compliance, to sign or initial all contracts, and to be in residence in the State during the time the entity's license is in effect or a project is under construction. The RME is held responsible for violations.

    From HAR 16-77-71 Principal and subordinate RMEs

Homeowner contracts and payment

The disclosures, written contract and subcontractor payment rules for residential work under HRS 444-25 and 444-25.5.

  1. 13. Before a homeowner signs a home improvement contract, what must a licensed contractor explain verbally in detail under HRS 444-25.5(a)?

    Show the answer

    C. The lien rights of all parties on the project and the homeowner's option to demand bonding. HRS 444-25.5(a) requires the contractor to explain verbally all lien rights of all parties, and the homeowner's option to demand bonding, how the bond would protect the homeowner and its approximate cost, and to disclose other contract information the board requires.

    From HRS 444-25.5 Disclosure; contracts

  2. 14. When must the written home improvement contract required by HRS 444-25.5(b) be signed by both parties?

    Show the answer

    A. Before any home construction or improvement work is performed. HRS 444-25.5(b) requires a written contract signed by the contractor and the homeowner and executed prior to the performance of any home construction or improvement.

    From HRS 444-25.5 Disclosure; contracts

  3. 15. Under HRS 444-25.5(b)(2), the written homeowner contract must contain notice of the contractor's right to do what before any litigation starts?

    Show the answer

    D. Resolve alleged construction defects (HRS 672E-11). HRS 444-25.5(b)(2) requires the contract to contain notice of the contractor's right to resolve alleged construction defects before commencing litigation, in accordance with HRS 672E-11.

    From HRS 444-25.5 Disclosure; contracts

  4. 16. Under HRS 444-25.5(d), a contractor's violation of the homeowner disclosure and contract requirements is treated as what?

    Show the answer

    B. An unfair or deceptive practice subject to chapter 480 as well as chapter 444. HRS 444-25.5(d) deems any violation an unfair or deceptive practice subject to chapter 480 and to chapter 444. Under chapter 480 the contract can be void, and Hawaii courts have denied a lien to a contractor who skipped the lien disclosures.

    From HRS 444-25.5 Disclosure; contracts

  5. 17. Which item must a written homeowner contract contain under HAR 16-77-80(a)?

    Show the answer

    C. The exact dollar amount due from the homeowner under the contract. HAR 16-77-80(a) lists the contractor's name, address, license number and classifications; the exact dollar amount due; the start date and days to completion; the scope and materials; subcontracting information; a risk-of-loss statement for payments to a sales representative; lien rights; warranty terms; and both signatures.

    From HAR 16-77-80 Homeowner contracts

  6. 18. Under HRS 444-25, an unpaid subcontractor is entitled to interest on the overdue amount at what rate per month (absent a bona fide dispute)?

    Show the answer

    A. One and one-half percent. HRS 444-25 requires the contractor to pay the subcontractor within ten days after receiving the subcontractor's invoice and the owner's payment for that work, whichever is later. Interest runs at one and one-half per cent per month from the date payment is due.

    From HRS 444-25 Payment for goods and services

Recovery fund, penalties and records

The contractors recovery fund, assessments, fines and what a licensee must keep on file.

  1. 19. What is the most the contractors recovery fund can pay for damages per contract under HRS 444-26(a), regardless of how many persons were injured?

    Show the answer

    D. $12,500. HRS 444-26(a) limits recovery to not more than $12,500 per contract, and only to actual damages, including court costs and reasonable attorney fees as the court decides.

    From HRS 444-26 Contractors recovery fund

  2. 20. Who may recover from the contractors recovery fund as a "person injured" under HRS 444-26(b)?

    Show the answer

    B. Owners or lessees of private residences who contracted with a duly licensed contractor for work on their own residences. HRS 444-26(b) limits "person injured" to owners or lessees of private residences (including condominium and cooperative units) who contracted with a duly licensed contractor for improvements to, or construction of, their own residences.

    From HRS 444-26 Contractors recovery fund

  3. 21. A homeowner signs a contract with a contractor whose license was suspended on that date. After a loss, can the homeowner collect from the contractors recovery fund?

    Show the answer

    C. No, the fund does not pay for acts of a contractor whose license was suspended, revoked, forfeited, terminated or inactive when the contract was made. HRS 444-26(a) says recovery shall not be awarded for conduct of a contractor whose license was suspended, revoked, forfeited, terminated, or in an inactive status at the time the claimant entered into the contract.

    From HRS 444-26 Contractors recovery fund

  4. 22. When the contractors recovery fund balance is below $250,000, the board may assess every contractor a fee of not more than what amount annually under HRS 444-27?

    Show the answer

    A. $500. HRS 444-27(a) allows an assessment not to exceed $500 annually when the balance is under $250,000. Under 444-27(b), failure to pay within sixty days of the assessment forfeits the license.

    From HRS 444-27 Additional payments to fund

  5. 23. Under HRS 444-23(a), what is the fine for a licensee who contracts outside the scope of the licensed classification, for the first offense?

    Show the answer

    D. $500. HRS 444-23(a) sets $500 for the first offense, $1,000 for the second, and not less than $1,500 or more than $2,000 for any later offense.

    From HRS 444-23 Violation; penalties

  6. 24. An unlicensed person is fined for a first offense of acting as a contractor without a license (HRS 444-9) on a $20,000 contract. Under HRS 444-23(c)(1), what is the fine, the greater of $2,500 or forty per cent of the total contract price?

    Show the answer

    B. $8,000. Forty per cent of $20,000 is $8,000, which is greater than $2,500, so the first-offense fine is $8,000. Second offenses are $3,500 or forty per cent, and later offenses $5,000 or forty per cent, whichever is greater.

    From HRS 444-23 Violation; penalties

  7. 25. Under HRS 444-17(7), failing to keep records of all of a licensee's contracting transactions for less than how long after completion of the project is grounds for discipline?

    Show the answer

    C. Three years. HRS 444-17(7) makes it a ground for revocation, suspension or refusal to renew to fail to make and keep records of contracts, documents, receipts and disbursements for not less than three years after completion of the project, or to permit the board to inspect them.

    From HRS 444-17 Revocation, suspension, and renewal of licenses

Liens, workers' comp and tax

Hawaii's mechanic's and materialman's lien (HRS chapter 507, part II), workers' compensation security and the general excise tax on contractors.

  1. 26. Under HRS 507-43(b), an Application and Notice of Lien must be filed not later than how many days after the date of completion of the improvement?

    Show the answer

    A. Forty-five. HRS 507-43(b) requires filing with the circuit court not later than forty-five days after completion of the improvement against which the lien is claimed.

    From HRS 507-43 Filing notice, contents

  2. 27. Under HRS 507-43(a), the Application and Notice of Lien is returnable how long after service on the owner?

    Show the answer

    D. Not less than three nor more than ten days. HRS 507-43(a) sets the return day not less than three nor more than ten days after service, when the court hears whether probable cause exists. The lien does not attach until the court finds probable cause and so orders.

    From HRS 507-43 Filing notice, contents

  3. 28. An owner wants to discharge a $15,000 mechanic's lien by filing cash or a bond under HRS 507-45. What amount of cash or bond must be filed?

    Show the answer

    B. $30,000. HRS 507-45 allows discharge by filing with the clerk of the circuit court cash or a bond for twice the amount of the claim. Twice $15,000 is $30,000.

    From HRS 507-45 Discharge of lien

  4. 29. Under HRS 507-46, liens for wages for labor on the improvement have priority as a class over other mechanics' and materialmen's liens up to what amount per claimant?

    Show the answer

    C. $300. HRS 507-46 gives wage liens priority as a class, not exceeding $300 for each claimant, when filed by the worker, the worker's representative or the director of labor and industrial relations. Other liens take effect from the visible commencement of operations.

    From HRS 507-46 Priority, record of; satisfaction

  5. 30. On a home that was used mainly as a dwelling, can a supplier get a mechanic's lien for materials sold to a general contractor who was required to be licensed but was not (HRS 507-49)?

    Show the answer

    A. No, no lien exists for materials furnished to an unlicensed general contractor who was required to be licensed. HRS 507-49(a) says that on repairs or improvements to property used primarily for dwelling purposes, no lien exists for materials furnished to a general contractor or subcontractor who was required to be licensed under chapter 444 but was not, or where unreasonable credit was advanced.

    From HRS 507-49 Exceptions

  6. 31. Under HRS 386-121(a), how must a private employer in Hawaii secure workers' compensation for its employees?

    Show the answer

    D. By insuring with an authorized insurer, or by security or self-insurance approved by the director of labor and industrial relations. HRS 386-121(a) requires employers (other than government) to secure compensation by insuring with an authorized insurer, depositing approved security with the director of finance, or showing solvency to the director, among other approved methods. HRS 444-11.1 makes keeping this coverage a condition of the license.

    From HRS 386-121 Security for payment of compensation

  7. 32. Before any county surcharge, what percentage of the gross income of a contracting business does the Hawaii general excise tax impose on contractors under HRS 237-13(3)(A)?

    Show the answer

    B. Four percent. HRS 237-13(3)(A) levies a tax equal to four per cent of the gross income of the business on every person engaging in contracting. The one-half of one per cent rate applies to wholesale sales, not contracting.

    From HRS 237-13(3)(A) Imposition of general excise tax, tax upon contractors

0 of 32 answered

Setting up your own shop

Beyond the license in Hawaii, a new contracting business needs a way to schedule and bill jobs, insurance and, where the state asks for one, a bond.

Offered to tradespeople starting their own business. We may earn a share of what you pay if you buy through these links. It never changes your price, and the sellers have no say in what we publish about licensing.

Questions

Are these the real Hawaii Business and Law Exam exam questions?

No. The bodies that give the real exam keep its questions to themselves. Each question here is written for the rules or skills the exam tests, and its explanation shows the working or names the section of the regulation or code it comes from, so you learn the rule rather than one answer.

Is the practice test free?

Yes. All 32 questions and their explanations are free, with no sign-up. Your answers stay in your browser.

Checked against the rules in force on 2026-11-26. Rules and exam formats change: check the current rule and your exam provider's own information before the exam.