Louisiana Business and Law Exam Practice Test

Practice for the Business and Law exam Louisiana's contractor board asks of commercial, residential and home improvement applicants, on what is Louisiana's own: who needs which license, the Private Works Act, public works, workers' comp and Louisiana employer rules. Pick an answer to see whether it is right and the statute behind it.

39
practice questions
each with its answer explained
5
sections
Who needs a license, Applying, qualifying party and renewal, Exemptions, bids and penalties, Liens and the Private Works Act, Public works, home warranty and workers' comp
70%
to pass the real exam
as its official rules state

What the real exam is like

Passing it, with any trade exam your classification requires, is what the Louisiana State Licensing Board for Contractors asks of the qualifying party before it issues a license.

  • A Louisiana license applicant designates a qualifying party for each classification and for the Louisiana business and law requirement. The qualifying party must satisfy every examination and credential requirement. (La. R.S. 37:2156.1(E)(1))
  • The Louisiana Business and Law exam is taken online from the qualifying party's LSLBC Contractor Licensing Portal after an Examination Approval Notice is emailed. It is 50 questions, takes about 30 to 45 minutes, and you must score 70 or above to pass. (LSLBC, What Happens After I Apply (Step 4))
  • A qualifying party who has already completed Louisiana Business and Law does not get a new approval notice. An exam fee is due for each classification and for Business and Law. (LSLBC, Frequently Asked Questions)
  • Trade exams are separate: since 5 August 2025 they are given by PSI, with scheduling and payment through PSI after an eligibility letter from the board. (LSLBC, PSI Testing Notice)

The practice test

Pick an answer to see whether it is right. Each explanation shows why, with the rule or the working behind it, so a wrong answer still teaches you something.

0 of 39 answered

Who needs a license (8) · Applying, qualifying party and renewal (7) · Exemptions, bids and penalties (8) · Liens and the Private Works Act (8) · Public works, home warranty and workers' comp (8)

Who needs a license

The job value lines for each license type and how project value is counted under La. R.S. 37:2150.1 and 37:2158.

  1. 1. Under the Louisiana contractor licensing law, a person who bids on a commercial construction undertaking (other than electrical, mechanical, plumbing or hazardous materials work) is a contractor requiring a license when the project value is at least what amount?

    Show the answer

    C. $50,000. A contractor for commercial purposes is defined by a project value of fifty thousand dollars or more. Electrical, mechanical and plumbing work has a lower $10,000 line.

    From La. R.S. 37:2150.1(4)(a)(i)

  2. 2. A home improvement contractor is a person who takes on a home improvement project with a project value in which range?

    Show the answer

    D. At least $7,500 but less than $50,000. Home improvement is defined from $7,500 up to (but not including) $50,000. At $50,000 or more the work falls under a residential contractor license.

    From La. R.S. 37:2150.1(11)

  3. 3. For the definition of a residential contractor building a residence for use by another, what is the greatest height of the structure?

    Show the answer

    B. Not more than three floors. The statute covers a residential structure which is not more than three floors in height, with a project value of fifty thousand dollars or more.

    From La. R.S. 37:2150.1(19)(a)

  4. 4. What project value makes a person an electrical contractor, who must hold an electrical license, under the definition in R.S. 37:2150.1?

    Show the answer

    A. $10,000 or more. An electrical contractor is defined by wiring, fixtures or appliances work for the supply of electricity at a project value of ten thousand dollars or more. Mechanical and plumbing contractors use the same $10,000 line.

    From La. R.S. 37:2150.1(6)

  5. 5. A contractor holding a license in the hazardous materials major classification is defined in terms of work performed with a project value of what amount?

    Show the answer

    C. One dollar or more. Paragraph (4)(c) sets hazardous materials at one dollar or more, so there is no dollar floor in practice.

    From La. R.S. 37:2150.1(4)(c)

  6. 6. How is project value counted to decide whether a Louisiana contractor license is required?

    Show the answer

    D. The entire cost of labor, materials, rentals and all direct and indirect expenses, regardless of who pays or whether the items are donated. The statute says the project value includes the entire cost of labor, materials, rentals and all direct and indirect project expenses, no matter who pays them or whether they are donated.

    From La. R.S. 37:2150.1(3)

  7. 7. An owner splits one $80,000 commercial scope of work into two $40,000 contracts to stay under the license threshold. How does the board treat this?

    Show the answer

    B. The divided parts are treated as one scope of work when deciding whether a license is required. R.S. 37:2158(B)(1) disregards any division of a contract or scope of work that would avoid the need for a license and treats the parts as one.

    From La. R.S. 37:2158(B)(1)

  8. 8. Which work is a home improvement contractor barred from performing?

    Show the answer

    A. Structural work integral to the structure, such as footings, foundations, bearing walls and roofing systems. A home improvement contractor shall not perform structural work integral to the structural integrity of a structure, including footings, foundations, outside walls, bearing columns, interior load bearing walls, floor slabs or roofing systems.

    From La. R.S. 37:2150.1(11)

Applying, qualifying party and renewal

Net worth, the qualifying party, the renewal calendar and testing exemptions under La. R.S. 37:2156 and 37:2156.1.

  1. 9. What net worth must an applicant for a commercial or residential contractor license (not labor only, home improvement or mold remediation) have?

    Show the answer

    B. $50,000 or more. Residential and commercial licenses, their subclassifications and specialty classifications (except labor only) need a net worth of fifty thousand dollars or more. An irrevocable letter of credit can make up a shortfall.

    From La. R.S. 37:2156.1(B)(2)

  2. 10. What net worth is required for a home improvement, mold remediation or labor only specialty applicant?

    Show the answer

    A. $25,000 or more. Home improvement, mold remediation and labor only specialties need a net worth of twenty-five thousand dollars or more.

    From La. R.S. 37:2156.1(B)(2)

  3. 11. When a licensee's qualifying party is no longer associated with the license, the board must be notified within how many days, and another qualifying party must qualify within how many days?

    Show the answer

    C. Notify within 30 days; qualify within 60 days. The board is notified within thirty days of the disassociation and another qualifying party must qualify within sixty days.

    From La. R.S. 37:2156.1(E)(1)

  4. 12. After a Louisiana contractor license expires, how long does the licensee have to file a renewal application without paying a penalty?

    Show the answer

    D. Fifteen days after the expiration date. The licensee has fifteen days following the expiration date to file for renewal without penalty. After that a delinquent fee (not more than $50) is charged.

    From La. R.S. 37:2156(H)(1)

  5. 13. A license has not been renewed for more than one year after its expiration date. What is the result?

    Show the answer

    B. It can no longer be renewed, and the person must apply for a new license. If a license is not renewed within one year from the date of its expiration, it is no longer eligible for renewal. A new application can be filed and, once approved, a new license is issued.

    From La. R.S. 37:2156(J)

  6. 14. Who may serve as the qualifying party of an applicant or licensee, once all requirements are met?

    Show the answer

    A. Any principal or full-time employee. Any principal or full-time employee as defined in the Chapter may be the qualifying party upon satisfying all requirements.

    From La. R.S. 37:2156.1(E)(2)

  7. 15. A person holds a building construction license issued by the board. What does the law say about testing for a residential construction license?

    Show the answer

    D. The board shall exempt the person from testing for the residential construction license. The board shall exempt from testing for a residential construction license any person who holds a building construction license issued by the board.

    From La. R.S. 37:2156.1(E)(4)

Exemptions, bids and penalties

Who is exempt, the bid envelope rule and the penalties under La. R.S. 37:2157, 37:2158, 37:2163 to 37:2165.

  1. 16. An owner supervises construction of his own personal residence without a contractor license. What limit applies to this exemption?

    Show the answer

    C. The owner may not build more than one residence per year (the year runs from the certificate of occupancy). R.S. 37:2157(A)(13) exempts owners working on their personal residence if they do not build more than one residence per year, and an affidavit of exemption is needed to get the building permit.

    From La. R.S. 37:2157(A)(13)

  2. 17. Which person needs no contractor license under R.S. 37:2157 for the project described?

    Show the answer

    A. A person bidding or performing work on a project totally owned by the federal government. Exemption (A)(5) covers any person bidding or performing work on a project totally owned by the federal government. State and local public work is not exempt.

    From La. R.S. 37:2157(A)(5)

  3. 18. On a Louisiana public bid for work that requires a license, what must the contractor show on the bid envelope, and what happens if it is missing?

    Show the answer

    B. The license number; the bid is automatically rejected, returned marked Rejected and not read aloud. A contractor certifies an active license by displaying the license number on the bid envelope. Without it the bid is automatically rejected, returned marked Rejected and not read aloud.

    From La. R.S. 37:2165(A)(1)

  4. 19. A person who acts as a contractor without a license is guilty of a misdemeanor. What is the maximum fine per day of violation under R.S. 37:2163(C)(1)?

    Show the answer

    D. $500 per day (or three months in prison, or both). Violators face a fine not to exceed five hundred dollars per day, or three months in prison, or both. Harm over $300 carries heavier penalties.

    From La. R.S. 37:2163(C)(1)

  5. 20. After a license or qualifying party status is revoked, how long is the person ineligible to apply again?

    Show the answer

    A. Three years. The person or qualifying party is ineligible for three years after revocation and must then appear before the board for approval.

    From La. R.S. 37:2158(C)

  6. 21. The board's civil fine for violating the licensing law can be up to what share of the total contract or the value of the work bid or performed?

    Show the answer

    B. Ten percent. Any person who violates the Chapter is liable, after notice and a hearing, for a fine of up to ten percent of the total contract or value of the work. Violations with no determinable value carry up to $10,000.

    From La. R.S. 37:2164(A)

  7. 22. How long must a licensee keep records for the board, and how fast must it provide them when asked?

    Show the answer

    C. Five years; within five business days of the request. Records must be maintained for five years and provided within five business days of receipt of the request.

    From La. R.S. 37:2156.2(A)

  8. 23. Under the board's list of violations, what is wrong with doing a job without a written contract?

    Show the answer

    A. It is a violation to fail to have a written contract signed and dated by all parties. R.S. 37:2158(A)(20) lists failure to have a written contract signed and dated by all parties as a ground for board action.

    From La. R.S. 37:2158(A)(20)

Liens and the Private Works Act

Notice of contract, bonds, filing deadlines and enforcement under La. R.S. 9:4801 and following.

  1. 24. Under the Private Works Act, what is the minimum amount of the bond an owner requires of a general contractor (to give the owner relief from subcontractor claims)?

    Show the answer

    B. Not less than the price of the work stated or estimated in the notice of contract. R.S. 9:4812(B): the amount of the bond shall not be less than the price of the work stated or estimated in the notice of contract.

    From La. R.S. 9:4812(B)

  2. 25. A general contractor's contract price exceeds $100,000 and no notice of contract is timely filed. What is the effect on the contractor?

    Show the answer

    D. He has no privilege under the Part and may not file a statement of claim or privilege. R.S. 9:4811(D): a general contractor enjoys no privilege if the price exceeds one hundred thousand dollars unless notice of the contract is timely filed.

    From La. R.S. 9:4811(D)

  3. 26. No notice of contract was filed and no notice of termination of the work was filed. A subcontractor must file a statement of claim or privilege no later than how long after substantial completion or abandonment of the work?

    Show the answer

    A. Sixty days. R.S. 9:4822(A): a claimant files no later than sixty days after the notice of termination, or after substantial completion or abandonment if no notice of termination is filed.

    From La. R.S. 9:4822(A)

  4. 27. A notice of contract was timely filed and no notice of termination was filed. A subcontractor holding a claim under R.S. 9:4802 must file its statement of claim and deliver a copy to the owner within what time after substantial completion or abandonment?

    Show the answer

    C. Six months. R.S. 9:4822(B)(2) gives six months after substantial completion or abandonment (or thirty days after a notice of termination is filed).

    From La. R.S. 9:4822(B)

  5. 28. A general contractor whose privilege was preserved by a timely notice of contract and who has no notice of termination must file his statement of privilege within what time after substantial completion or abandonment?

    Show the answer

    B. Seven months. R.S. 9:4822(C)(2) gives the general contractor seven months, one month longer than subcontractors in the same situation.

    From La. R.S. 9:4822(C)

  6. 29. After a statement of claim or privilege is filed, within what time must the holder sue the owner to enforce it before it is extinguished?

    Show the answer

    A. One year after filing the statement. R.S. 9:4823(A)(2): the claim or privilege is extinguished if no action is instituted against the owner within one year after filing the statement.

    From La. R.S. 9:4823(A)(2)

  7. 30. When an interested person deposits a bond or cash with the recorder of mortgages to cancel a filed privilege, the security may be up to what share of the principal amount of the claim asserted?

    Show the answer

    D. 125 percent. R.S. 9:4835(A): the bond, cash or certified funds cover the obligation plus interest, costs and fees, up to one hundred twenty-five percent of the principal amount of the claim.

    From La. R.S. 9:4835(A)

  8. 31. For a seller to compel the surety on a general contractor's bond to pay under R.S. 9:4812(F), the seller sends a notice of nonpayment no sooner than how many days after delivery of the movables?

    Show the answer

    C. Forty-five days. The notice goes to the general contractor, the surety and the owner no sooner than forty-five days after delivery, and the seller must still be unpaid at ninety days after delivery. The surety then pays within ten days.

    From La. R.S. 9:4812(F)(2)

Public works, home warranty and workers' comp

Bonds, claims, retainage, prompt pay and advertising for public work, the builder's warranty and who can be sued for workers' compensation.

  1. 32. For a public works contract in excess of what amount per project must a Louisiana public entity require a payment bond from the contractor?

    Show the answer

    D. $25,000. R.S. 38:2241(A)(2): each contract in excess of twenty-five thousand dollars per project needs a bond. (A written contract is required once the contract exceeds $5,000.)

    From La. R.S. 38:2241(A)(2)

  2. 33. The public works bond and contract are recorded with the recorder of mortgages in the parish where the work is done no later than when?

    Show the answer

    B. Thirty days after the work has begun. The bond is recorded with the contract not later than thirty days after the work has begun.

    From La. R.S. 38:2241(A)(2)

  3. 34. A claimant on a public work files a sworn statement of the amount due within how many days after recordation of acceptance of the work or notice of default?

    Show the answer

    C. Forty-five days. R.S. 38:2242(B): within forty-five days after recordation of acceptance of the work or notice of default, the claimant files the sworn statement with the governing authority and records it with the recorder of mortgages.

    From La. R.S. 38:2242(B)

  4. 35. Under R.S. 38:2248(A), what is the most a public entity may contractually withhold on a $600,000 public works contract (not a flood or coastal protection liquidated damages case)?

    Show the answer

    B. $30,000 (5 percent). Retainage may not exceed ten percent on projects under $500,000 and five percent on projects of $500,000 or more. Five percent of $600,000 is $30,000.

    From La. R.S. 38:2248(A)

  5. 36. If a public entity fails without reasonable cause to pay a progressive stage payment within 45 days of a certified request, interest is charged at one-half percent accumulated daily, up to what cap?

    Show the answer

    D. Fifteen percent. R.S. 38:2191(B)(1) sets interest at one-half percent accumulated daily, not to exceed fifteen percent, plus reasonable attorney fees.

    From La. R.S. 38:2191(B)(1)

  6. 37. The newspaper advertisement for a public works bid runs once a week for three different weeks. How long before bid opening must the first one appear?

    Show the answer

    A. At least 25 days. R.S. 38:2212(G)(1): published once a week for three different weeks in a newspaper in the locality, the first at least twenty-five days before bids open.

    From La. R.S. 38:2212(G)(1)

  7. 38. Under the New Home Warranty Act, how long after the warranty commencement date is a builder's warranty on the plumbing, electrical, heating, cooling and ventilating systems (not appliances and fixtures)?

    Show the answer

    C. Two years. R.S. 9:3144(A): one year for defects in the home generally, two years for those systems, and five years for major structural defects.

    From La. R.S. 9:3144(A)

  8. 39. Under La. R.S. 23:1062, may an injured worker recover workers' compensation from the contractor (his immediate employer) instead of from the principal?

    Show the answer

    B. Yes, the statute on principal contractors does not prevent recovery from the contractor instead of the principal. R.S. 23:1062 says nothing in the principal contractor section prevents an employee or dependent from recovering compensation from the contractor instead of from the principal.

    From La. R.S. 23:1062

0 of 39 answered

Setting up your own shop

Beyond the license in Louisiana, a new contracting business needs a way to schedule and bill jobs, insurance and, where the state asks for one, a bond.

Offered to tradespeople starting their own business. We may earn a share of what you pay if you buy through these links. It never changes your price, and the sellers have no say in what we publish about licensing.

Questions

Are these the real Louisiana Business and Law Exam exam questions?

No. The bodies that give the real exam keep its questions to themselves. Each question here is written for the rules or skills the exam tests, and its explanation shows the working or names the section of the regulation or code it comes from, so you learn the rule rather than one answer.

Is the practice test free?

Yes. All 39 questions and their explanations are free, with no sign-up. Your answers stay in your browser.

Checked against the rules in force on 2026-11-26. Rules and exam formats change: check the current rule and your exam provider's own information before the exam.